[PDF] By Southern Indiana Gas and Electric Company d/b/a Vectren Energy Delivery of Indiana, Incorporated - Free Download PDF (2024)

Download By Southern Indiana Gas and Electric Company d/b/a Vectren Energy Delivery of Indiana, Incorporated...

By Southern Indiana Gas and Electric Company d/b/a Vectren Energy Delivery of Indiana, Incorporated November 1, 2014

2014 Integrated Resource Plan

November 2014

2014 Integrated Resource Plan

PAGE 1. EXECUTIVE SUMMARY COMPANY BACKGROUND .............................................................................19 THE IRP PROCESS ........................................................................................ 20 VECTREN’S QUANTITATIVE AND QUALITATIVE IRP PROCESS............... ..21 CHANGES SINCE LAST IRP.......................................................................... ..22 PLAN RESULTS/RECOMMENDATIONS ....................................................... ..25 CONCLUSION ................................................................................................ ..26 2. PLANNING PROCESS INTRODUCTION............................................................................................. ..31 PLANNING PROCESS ................................................................................... ..31 3. MISO INTRODUCTION............................................................................................. ..38 MISO OVERVIEW........................................................................................... ..38 MISO’S GOALS .............................................................................................. ..40 MISO PLANNING PROCESS ......................................................................... ..41 DEMAND RESPONSE .................................................................................... ..47 MISO FORECAST .......................................................................................... ..47 4. ENVIRONMENTAL INTRODUCTION............................................................................................. ..51 CURRENT ENVIRONMENTAL COMPLIANCE PROGRAMS ........................ ..51 AIR .................................................................................................................. ..51 SOLID WASTE DISPOSAL ............................................................................. ..57 HAZARDOUS WASTE DISPOSAL ................................................................. ..58 WATER ........................................................................................................... ..58 FUTURE ENVIRONMENTAL REGULATIONS ............................................... ..59 CARBON REGULATION ................................................................................ ..59 WASTE DISPOSAL ........................................................................................ ..60 WATER ........................................................................................................... ..61 5. SALES & DEMAND FORECAST INTRODUCTION............................................................................................. ..66 ELECTRIC LOAD FORECAST OVERVIEW ................................................... ..66 FORECAST RESULTS ................................................................................... ..67 FORECAST INPUTS & METHODOLOGY ...................................................... ..72 CUSTOMER OWNED DISTRIBUTED GENERATION FORECAST ............... ..84 OVERVIEW OF LOAD RESEARCH ACTIVITIES ........................................... ..89 APPLIANCE SATURATION SURVEY & CONTINUOUS IMPROVEMENT .... ..92 OVERVIEW OF PAST FORECASTS .............................................................. ..93

November 2014 Page 1

2014 Integrated Resource Plan

PAGE 6. ELECTRIC SUPPLY ANALYSIS INTRODUCTION............................................................................................. 99 TECHNOLOGY ASSESSMENT...................................................................... 99 NEW CONSTRUCTION ALTERNATIVE SCREENING .................................108 PURCHASED POWER ALTERNATIVES ......................................................111 CUSTOMER SELF-GENERATION ................................................................112 RENEWABLE TECHNOLOGIES ...................................................................112 7. RENEWABLES and CLEAN ENERGY CURRENT PROJECTS .................................................................................116 RENEWABLE ENERGY CREDITS ................................................................116 ADDITIONAL RENEWABLE AND CLEAN ENERGY CONSIDERATIONS ...117 8. DSM RESOURCES INTRODUCTION............................................................................................121 HISTORICAL PERFORMANCE .....................................................................121 EXISTING DSM RESOURCES AND PROGRAMS .......................................122 FEDERAL AND STATE ENERGY EFFICIENCY DEVELOPMENTS .............129 VECTREN DSM STRATEGY .........................................................................131 DSM PLANNING PROCESS .........................................................................132 DSM SCREENING RESULTS .......................................................................137 2015 ELECTRIC DSM PLAN – CAUSE NO. 44495.......................................152 IRP DSM MODELING ....................................................................................171 9. TRANSMISSION AND DISTRIBUTION PLANNING INTRODUCTION............................................................................................175 METHODOLOGY ...........................................................................................176 SYSTEM INTEGRITY ANALYSIS – 2013 (SEASONAL, ANNUAL, INCLUDES SPRING, SUMMER, FALL, AND WINTER) ................................177 SYSTEM INTEGRITY ANALYSIS – 2018 (NEAR TERM-WITHIN 1-5 YEARS) ...................................................................................................178 SYSTEM INTEGRITY ANALYSIS – 2022 (LONG TERM 6-10 YEARS) ........178 TRANSMISSION ADEQUACY SUMMARY TABLE ......................................178 RECOMMENDATIONS: 2014-2034 ...............................................................180 COST PROJECTIONS ...................................................................................182 10. GENERATION PLANNING INTRODUCTION............................................................................................186 APPROACH ...................................................................................................186 DISCUSSION OF KEY INPUTS AND ASSUMPTIONS .................................188 INTEGRATION ANALYSIS RESULTS ...........................................................193 SENSITIVITY AND RISK ANALYSIS .............................................................202 CONCLUSION ...............................................................................................211 November 2014 Page 2

2014 Integrated Resource Plan

PAGE 11. ACTION PLAN INTRODUCTION............................................................................................215 SUPPLY-SIDE RESOURCES ........................................................................215 DEMAND-SIDE RESOURCES ......................................................................215 TRANSMISSION AND DISTRIBUTION .........................................................216 IRP Proposed Draft Rule Requirements Cross Reference Table

Rule Reference 170 IAC 4-7-4

Rule Description Methodology and documentation requirements

Report Reference (As Page # or Attachment)

(a) The utility shall provide an IRP summary document that communicates core IRP concepts and results to non-technical audiences. (1) The summary shall provide a brief description of the utility’s existing resources, preferred resource portfolio, short term action plan, key factors influencing the preferred resource portfolio and short term action plan, and any additional details the commission staff may request as part of a contemporary issues meeting. The summary shall describe, in simple terms, the IRP public advisory process, if applicable, and core IRP concepts, including resource types and load characteristics.

Technical Appendix J and www.vectren.com/irp

(2) The utility shall utilize a simplified format that visually portrays the summary of the IRP in a manner that makes it understandable to a non-technical audience. (3) The utility shall make this document readily accessible on its website. (b) An IRP must include the following: (1) A discussion of the: (A) inputs; (B) methods; and

Included throughout the IRP

(C) definitions; used by the utility in the IRP.

November 2014 Page 3

2014 Integrated Resource Plan

Rule Reference

170 IAC 4-7-4 Cont.

Rule Description (2) The data sets, including data sources, used to establish base and alternative forecasts. A third party data source may be referenced. The reference must include the source title, author, publishing address, date, and page number of relevant data. The data sets must include an explanation for adjustments. The data must be provided on electronic media, and may be submitted as a file separate from the IRP, or as specified by the commission.

Report Reference (As Page # or Attachment)

72, 190-191, Technical Appendix sections: A, B, D, E, F, I

(3) A description of the utility's effort to develop and maintain a data base of electricity consumption patterns, by customer class, rate class, NAICS code, and end-use. The data base may be developed using, but not limited to, the following methods: (A) Load research developed by the individual utility. (B) Load research developed in conjunction with another utility.

72

(C) Load research developed by another utility and modified to meet the characteristics of that utility. (D) Engineering estimates. (E) Load data developed by a non-utility source. (4) A proposed schedule for industrial, commercial, and residential customer surveys to obtain data on end-use appliance penetration, end-use saturation rates, and end-use electricity consumption patterns.

92

(5) A discussion of distributed generation within the service territory and the potential effects on generation, transmission, and distribution planning and load forecasting.

84-85

(6) A complete discussion of the alternative forecast scenarios developed and analyzed, including a justification of the assumptions and modeling variables used in each scenario.

66-89, 186-200

(7) A discussion of how the utility’s fuel inventory and procurement planning practices, have been taken into account and influenced the IRP development.

190

(8) A discussion of how the utility’s emission allowance inventory and procurement practices for any air emission regulated through an emission allowance system have been taken into account and influenced the IRP development.

51-55

(9) A description of the generation expansion planning criteria. The description must fully explain the basis for the criteria selected.

186-192

November 2014 Page 4

2014 Integrated Resource Plan

Rule Reference

Rule Description

Report Reference (As Page # or Attachment)

(10) A brief description and discussion within the body of the IRP focusing on the utility’s Indiana jurisdictional facilities with regard to the following components of FERC Form 715: (A) Most current power flow data models, studies, and sensitivity analysis.

170 IAC 4-7-4 Cont.

(B) Dynamic simulation on its transmission system, including interconnections, focused on the determination of the performance and stability of its transmission system on various fault conditions. The simulation must include the capability of meeting the standards of the North American Electric Reliability Corporation (NERC).

175-183

(C) Reliability criteria for transmission planning as well as the assessment practice used. The information and discussion must include the limits set of its transmission use, its assessment practices developed through experience and study, and certain operating restrictions and limitations particular to it. (D) Various aspects of any joint transmission system, ownership, and operations and maintenance responsibilities as prescribed in the terms of the ownership, operation, maintenance, and license agreement. (11) An explanation of the contemporary methods utilized by the utility in developing the IRP, including a description of the following: (A) Model structure and reasoning for use of particular model or models in the utility’s IRP.

66-67, 186-187

(B) The utility's effort to develop and improve the methodology and inputs for its:

32, 186

(i) forecast;

32, 93

(ii) cost estimates;

32, 99, 190-191

(iii) treatment of risk and uncertainty; and

32, 190

(iv) evaluation of a resource (supply-side or demand-side) alternative’s contribution to system wide reliability. The measure of system wide reliability must cover the reliability of the entire system, including:

32

(AA) transmission; and

176-177

(BB) generation.

32

November 2014 Page 5

2014 Integrated Resource Plan

Rule Reference

170 IAC 4-7-4 Cont.

Rule Description (12) An explanation, with supporting documentation, of the avoided cost calculation. An avoided cost must be calculated for each year in the forecast period. The avoided cost calculation must reflect timing factors specific to the resource under consideration such as project life and seasonal operation. Avoided cost shall include, but is not limited to, the following: (A) The avoided generating capacity cost adjusted for transmission and distribution losses and the reserve margin requirement. (B) The avoided transmission capacity cost. (C) The avoided distribution capacity cost.

Report Reference (As Page # or Attachment)

139, Technical Appendix B

(D) The avoided operating cost, including fuel, plant operation and maintenance, spinning reserve, emission allowances, and transmission and distribution operation and maintenance. (13) The actual demand for all hours of the most recent historical year available, which shall be submitted electronically and may be a separate file from the IRP. For purposes of comparison, a utility must maintain three (3) years of hourly data.

170 IAC 4-7-5

(14) Publicly owned utilities shall provide a summary of the utility's: (A) most recent public advisory process; (B) key issues discussed; (C) how they were addressed by the utility. Energy and demand forecasts

Technical Appendix G

20-21, Technical Appendix A

(a) An electric utility subject to this rule shall prepare an analysis of historical and forecasted levels of peak demand and energy usage which includes the following: (1) Historical load shapes, including, but not limited to, the following: (A) Annual load shapes. (B) Seasonal load shapes. (C) Monthly load shapes. (D) Selected weekly and daily load shapes. Daily load shapes shall include, at a minimum, summer and winter peak days and a typical weekday and weekend day.

90-92, Technical Appendix C

(2) Historical and projected load shapes shall be disaggregated, to the extent possible, by customer class, interruptible load, and enduse and demand-side management program. (3) Disaggregation of historical data and forecasts by customer class, interruptible load, and end-use where information permits. (4) Actual and weather normalized energy and demand levels.

28, 69 90

November 2014 Page 6

2014 Integrated Resource Plan

Rule Reference 170 IAC 4-7-5 Cont.

Rule Description (5) A discussion of all methods and processes used to normalize for weather. (6) A minimum twenty (20) year period for energy and demand forecasts. (7) An evaluation of the performance of energy and demand forecasts for the previous ten (10) years, including, but not limited to, the following: (A) Total system. (B) Customer classes or rate classes, or both. (C) Firm wholesale power sales. (8) Justification for the selected forecasting methodology.

170IAC 4-7-6

Report Reference (As Page # or Attachment) 72-73 67-71

94-96

66-67, 76-77

(9) For purposes of subdivisions (1) and (2), a utility may use utility specific data or more generic data, such as, but not limited to, the types of data described in section 4(b)(2) of this rule.

89

(b) A utility shall provide at least three (3) alternative forecasts of peak demand and energy usage. At a minimum, the utility shall include high, low, and most probable energy and peak demand forecasts based on alternative assumptions such as:

70-71

(1) Rate of change in population. (2) Economic activity. (3) Fuel prices. (4) Changes in technology. (5) Behavioral factors affecting customer consumption. (6) State and federal energy policies. (7) State and federal environmental policies. Resource Assessment (a) The utility shall consider continued use of an existing resource as a resource alternative in meeting future electric service requirements. The utility shall provide a description of the utility's existing electric power resources that must include, at a minimum, the following information:

189

(1) The net dependable generating capacity of the system and each generating unit.

189

(2) The expected changes to existing generating capacity, including, but not limited to, the following: (A) Retirements. (B) Deratings. (C) Plant life extensions. (D) Repowering. (E) Refurbishment. (3) A fuel price forecast by generating unit.

28

190-191

November 2014 Page 7

2014 Integrated Resource Plan

Rule Reference

170IAC 4-7-6 Cont.

Rule Description (4) The significant environmental effects, including: (A) air emissions; (B) solid waste disposal; (C) hazardous waste; and (D) subsequent disposal; and

Report Reference (As Page # or Attachment)

51-58

(E) water consumption and discharge; at each existing fossil fueled generating unit. (5) An analysis of the existing utility transmission system that includes the following: (A) An evaluation of the adequacy to support load growth and expected power transfers. (B) An evaluation of the supply-side resource potential of actions to reduce transmission losses, congestion, and energy costs.

175-183

(C) An evaluation of the potential impact of demand-side resources on the transmission network. (D) An assessment of the transmission component of avoided cost. (6) A discussion of demand-side programs, including existing company-sponsored and government-sponsored or mandated energy conservation or load management programs available in the utility's service area and the estimated impact of those programs on the utility's historical and forecasted peak demand and energy.

69, 121-131, 152171

The information listed above in subdivision (a)(1) through subdivision (a)(4) and in subdivision (a)(6) shall also be provided for each year of the planning period. (b) An electric utility shall consider alternative methods of meeting future demand for electric service. A utility must consider a demandside resource, including innovative rate design, as a source of new supply in meeting future electric service requirements. The utility shall consider a comprehensive array of demand-side measures that provide an opportunity for all ratepayers to participate in DSM, including low-income residential ratepayers. For a utility-sponsored program identified as a potential demand-side resource, the utility's IRP shall, at a minimum, include the following: (1) A description of the demand-side program considered. (2) The avoided cost projection on an annual basis for the forecast period that accounts for avoided generation, transmission, and distribution system costs. The avoided cost calculation must reflect timing factors specific to resources under consideration such as project life and seasonal operation. (3) The customer class or end-use, or both, affected by the program. (4) A participant bill reduction projection and participation incentive to be provided in the program.

122-129

153-171

140

153-171 153-171

November 2014 Page 8

2014 Integrated Resource Plan

Rule Reference 170IAC 4-7-6 Cont.

Rule Description

Report Reference (As Page # or Attachment)

(5) A projection of the program cost to be borne by the participant.

153-171

(6) Estimated energy (kWh) and demand (kW) savings per participant for each program.

153-171

(7) The estimated program penetration rate and the basis of the estimate.

153-171

(8) The estimated impact of a program on the utility's load, generating capacity, and transmission and distribution requirements.

153-171

(c) A utility shall consider a range of supply-side resources including cogeneration and nonutility generation as an alternative in meeting future electric service requirements. This range shall include commercially available resources or resources the director may request as part of a contemporary issues technical conference. The utility's IRP shall include, at a minimum, the following:

109, 112

(1) Identify and describe the resource considered, including the following:

109

(A) Size (MW).

109

(B) Utilized technology and fuel type.

109

(C) Additional transmission facilities necessitated by the resource.

180-182

(2) A discussion of the utility's effort to coordinate planning, construction, and operation of the supply-side resource with other utilities to reduce cost.

N/A

(d) A utility shall consider new or upgraded transmission facilities as a resource in meeting future electric service requirements, including new projects, efficiency improvements, and smart grid resources. The IRP shall, at a minimum, include the following: (1) A description of the timing and types of expansion and alternative options considered. (2) The approximate cost of expected expansion and alteration of the transmission network.

175-183

(3) A description of how the IRP accounts for the value of new or upgraded transmission facilities for the purposes of increasing needed power transfer capability and increasing the utilization of cost effective resources that are geographically constrained.

November 2014 Page 9

2014 Integrated Resource Plan

Rule Reference

170IAC 4-7-6 Cont. 170 IAC 4-7-7

Rule Description (4) A description of how: (A) IRP data and information are used in the planning and implementation processes of the RTO of which the utility is a member; and

Report Reference (As Page # or Attachment)

38-48

(B) RTO planning and implementation processes are used in and affect the IRP. Selection of future resources (a) In order to eliminate nonviable alternatives, a utility shall perform an initial screening of all future resource alternatives listed in sections 6(b) through 6(c) of this rule. The utility's screening process and the decision to reject or accept a resource alternative for further analysis must be fully explained and supported in, but not limited to, a resource summary table. The following information: (1) Significant environmental effects, including the following: (A) Air emissions. (B) Solid waste disposal. (C) Hazardous waste and subsequent disposal. (D) Water consumption and discharge. (2) An analysis of how existing and proposed generation facilities conform to the utility-wide plan to comply with existing and reasonably expected future state and federal environmental regulations, including facility-specific and aggregate compliance options and associated performance and cost impacts.

109

188

(b) Integrated resource planning includes one (1) or more tests used to evaluate the cost effectiveness of a demand-side resource option. A cost-benefit analysis must be performed using the following tests except as provided under subsection (e): (1) Participant. (2) Ratepayer impact measure (RIM). (3) Utility cost (UC). (4) Total resource cost (TRC). (5) Other reasonable tests accepted by the commission. (c) A utility is not required to express a test result in a specific format. However, a utility must, in all cases, calculate the net present value of the program impact over the life cycle of the impact. A utility shall also explain the rationale for choosing the discount rate used in the test. (d) A utility is required to: (1) specify the components of the benefit and the cost for each of the major tests; and (2) identify the equation used to express the result.

137-151

138, 153-154

137-138 137

November 2014 Page 10

2014 Integrated Resource Plan

Rule Reference 170 IAC 4-7-7 Cont.

170 IAC 4-7-8

Rule Description

Report Reference (As Page # or Attachment)

(e) If a reasonable cost-effectiveness analysis for a demand-side management program cannot be performed using the tests in subsection (b), where it is difficult to establish an estimate of load impact, such as a generalized information program, the costeffectiveness tests are not required.

137-151

(f) To determine cost-effectiveness, the RIM test must be applied to a load building program. A load building program shall not be considered as an alternative to other resource options.

N/A

Resource integration (a) The utility shall develop candidate resource portfolios from the selection of future resources in section 7 and provide a description of its process for developing its candidate resource portfolios.

186-187

(b) From its candidate resource portfolios, a utility shall select a preferred resource portfolio and provide, at a minimum, the following information:

193-201

(1) Describe the utility's preferred resource portfolio.

193-194, 201

(2) Identify the variables, standards of reliability, and other assumptions expected to have the greatest effect on the preferred resource portfolio.

202-211

(3) Demonstrate that supply-side and demand-side resource alternatives have been evaluated on a consistent and comparable basis.

171-172

(4) Demonstrate that the preferred resource portfolio utilizes, to the extent practical, all economical load management, demand side management, technology relying on renewable resources, cogeneration, distributed generation, energy storage, transmission, and energy efficiency improvements as sources of new supply.

84-89, 109, 112, 122-132, 171-172

(5) Discuss the utility's evaluation of targeted DSM programs including their impacts, if any, on the utility's transmission and distribution system for the first ten (10) years of the planning period.

179, 137-140

November 2014 Page 11

2014 Integrated Resource Plan

Rule Reference

170 IAC 4-7-8 Cont.

Rule Description (6) Discuss the financial impact on the utility of acquiring future resources identified in the utility's preferred resource portfolio. The discussion of the preferred resource portfolio shall include, where appropriate, the following: (A) Operating and capital costs. (B) The average cost per kilowatt-hour, which must be consistent with the electricity price assumption used to forecast the utility's expected load by customer class in section 5 of this rule.

Report Reference (As Page # or Attachment)

N/A

(C) An estimate of the utility's avoided cost for each year of the preferred resource portfolio. (D) The utility's ability to finance the preferred resource portfolio. (7) Demonstrate how the preferred resource portfolio balances cost minimization with cost effective risk and uncertainty reduction, including the following. (A) Identification and explanation of assumptions. (B) Quantification, where possible, of assumed risks and uncertainties, which may include, but are not limited to: See below. (i) regulatory compliance; (ii) public policy; (iii) fuel prices; (iv) construction costs;

201-212

(v) resource performance; (vi) load requirements; (vii) wholesale electricity and transmission prices; (viii) RTO requirements; and (ix) technological progress. (C) An analysis of how candidate resource portfolios performed across a wide range of potential futures. (D) The results of testing and rank ordering the candidate resource portfolios by the present value of revenue requirement and risk metric(s). The present value of revenue requirement shall be stated in total dollars and in dollars per kilowatt-hour delivered, with the discount rate specified.

Technical Appendix H

November 2014 Page 12

2014 Integrated Resource Plan

Rule Reference 170 IAC 4-7-8 Cont.

Rule Description (E) An assessment of how robustness factored into the selection of the preferred resource portfolio.

Report Reference (As Page # or Attachment) 201-212

(8) Demonstrate, to the extent practicable and reasonable, that the preferred resource portfolio incorporates a workable strategy for reacting to unexpected changes. A workable strategy is one that allows the utility to adapt to unexpected circ*mstances quickly and appropriately. Unexpected changes include, but are not limited to, the following: See below. (A) The demand for electric service.

201-212

(B) The cost of a new supply-side or demand-side technology. (C) Regulatory compliance requirements and costs. (D) Other factors which would cause the forecasted relationship between supply and demand for electric service to be in error. 170 IAC 4-7-9

Short term action plan Sec. 9. A short term action plan shall be prepared as part of the utility's IRP, and shall cover each of the three (3) years beginning with the IRP submitted pursuant to this rule. The short term action plan is a summary of the preferred resource portfolio and its workable strategy, as described in 170 IAC 4-7-8(b)(8), where the utility must take action or incur expenses during the three (3) year period. The short term action plan must include, but is not limited to, the following: (1) A description of each resource in the preferred resource portfolio included in the short term action plan. The description may include references to other sections of the IRP to avoid duplicate descriptions. The description must include, but is not limited to, the following: (A) The objective of the preferred resource portfolio.

215-216

(B) The criteria for measuring progress toward the objective. (2) The implementation schedule for the preferred resource portfolio. (3) A budget with an estimated range for the cost to be incurred for each resource or program and expected system impacts. (4) A description and explanation of differences between what was stated in the utility’s last filed short term action plan and what actually transpired.

November 2014 Page 13

2014 Integrated Resource Plan

List of Acronyms/Abbreviations AC ACS AMI APWR ARRA ASPEN-OneLiner AUPC B BAGS BPJ BPM BTU CAA CAC CAES CAIR CAMR CCGT CCR CDD CEII CFL CHP CIL CO2 CPP CSAPR CVR CWA DA DGS DLC DOE DR DRR-1 DSM DSMA EAP ECM EDR EEFC EGU EIA EISA ELGS EPA EPRI ESP EVA FERC FF FGD GADS GDP GHG GS GWH HAP HCi

Air Conditioning American Community Survey Advanced Metering Infrastructure Advanced Pressurized Water Reactor American Recovery and Reinvestment Act Advanced Systems for Power Engineering, Incorporated Average Use Per Customer Water Heating Service – Closed to new customers Broadway Avenue Gas Turbines Best Professional Judgment MISO’s Business Practice Manual British Thermal Unit Clean Air Act Citizens Action Coalition Compressed Air Energy Storage Clean Air Interstate Rule Clean Air Mercury Rule Combined Cycle Gas Turbine Coal Combustion Residuals Cooling Degree Days Critical Electric Infrastructure Information Compact Fluorescent Lighting Combined Heat and Power Capacity Import Limit Carbon Dioxide Clean Power Plan Cross-State Air Pollution Rule Conservation Voltage Reduction Clean Water Act Distribution Automation Demand General Service Direct Load Control United States Department of Energy Demand Response Demand Response Resource Type 1 Demand-side Management Demand Side Management Adjustment Energy Assistance Program Electronically Commutated Motor Emergency Demand Response Energy Efficiency Funding Component Electric Generating Units Energy Information Administration Energy Independence and Security Act Effluent Limit Guidelines and Standards U.S. Environmental Protection Agency Electric Power Research Institute Electrostatic Precipitator Energy Ventures Analysis, Inc. Federal Energy Regulatory Commission Fabric Filter Flue Gas Desulfurization Generating Availability Data System Gross Domestic Product Greenhouse Gas General Service Gigawatt Hour Hazardous Air Pollutants Hydrochloric Acid

November 2014 Page 14

2014 Integrated Resource Plan

List of Acronyms/Abbreviations (continued) HDD HHV HLF HRSG HSPF HVAC ICAP IDEM IGCC IPP IRP IOU IURC kV kVA kWh LBA LCR LMR LP LRZ LOLE LSE MACT MAPE MARS MATS MECT MGD MISO MLA MMBTU MSA MTEP MW MWh NAICS NDC NERC NERC MOD NOAA NOx NPDES NPV NSPS O&M ORSANCO OSS OUCC OVEC PJM PM PRM PTI-PSS/E PV PVRR RBS

Heating Degree Days Higher Heating Value High Load Factor Heat Recovery Steam Generator Heating Seasonal Performance Factor Heating, Ventilation, and Air Conditioning Interconnection Installed Capacity Indiana Department of Environmental Management Integrated Gasification Combined Cycle Independent Power Producers Integrated Resource Plan Investor-Owned Utility Indiana Utility Regulatory Commission Kilovolt Kilovolt-Ampere Kilowatt Hour Load Balancing Area Local Clearing Requirement Load Management Receivers Large Power Local Resource Zone Loss of Load Expectation Load Serving Entity Maximum Achievable Control Technology Standards Mean Absolute Percentage Error Multi-Area Reliability Simulation mercury and Air Toxics Standards Module E Capacity Tracking Millions of Gallons per Day Midcontinent Independent System Operator Municipal Levee Authority One million British Thermal Unit Metropolitan Statistical Area MISO Transmission Expansion Plan Megawatt Megawatt Hour North American Industry Classification System Net Dependable Capacity North American Electric Reliability Council NERC Modeling, Data, and Analysis National Oceanic and Atmospheric Administration Nitrous Oxide National Pollutant Discharge Elimination System Net Present Value New Source Performance Standards Operation and Maintenance Ohio River Valley Sanitation Commission Off Season Service Office of Utility Consumer Counselor Ohio Valley Electric Corporation Pennsylvania New Jersey Maryland Interconnection LLC Particulate Matter Planning Reserve Margin Power Technologies Incorporated's Power System Simulator Program for Engineers Photovoltaic Present Value of Revenue Requirements Residential Behavioral Savings

November 2014 Page 15

2014 Integrated Resource Plan

List of Acronyms/Abbreviations (continued) RCRA REC RECB RFC RIM RPS RS SAE SCADA SCGT SCR SEER SGS SGT SIP SMR SO2 TPA TRC TVA UCAP VUHI ZRC

Resource Conservation and Recovery Act Renewable Energy Credit Regional Expansion Criteria and Benefits Reliability First Corporation Ratepayer Impact Measure Renewable Portfolio Standard Residential Service Statistically Adjusted End-use Supervisory Control and Data Acquisition Simple Cycle Gas Turbine Selective Catalytic Reduction Seasonal Energy Efficiency Ratio Small General Service Steam Turbine Generator System Integration Plan Small Modular Reactors Sulfur Dioxide Third Party Administrator Total Resource Cost Tennessee Valley Authority Unforced Capacity Rating Vectren Utility Holdings Inc. Zone Resource Credit

November 2014 Page 16

2014 Integrated Resource Plan

This page intentionally left blank for formatting purposes

November 2014 Page 17

2014 Integrated Resource Plan

CHAPTER 1 EXECUTIVE SUMMARY

November 2014 Page 18

2014 Integrated Resource Plan

COMPANY BACKGROUND Vectren Corporation is an energy holding company headquartered in Evansville, Indiana. Vectren’s wholly owned subsidiary, Vectren Utility Holdings, Inc. (VUHI), is the parent company for three operating utilities:

Indiana Gas Company, Inc. (Vectren

North), Southern Indiana Gas and Electric Company (Vectren), and Vectren Energy Delivery of Ohio (VEDO). Vectren North provides energy delivery services to more than 570,000 natural gas customers located in central and southern Indiana. Vectren provides energy delivery services to over 142,000 electric customers and approximately 110,000 gas customers located near Evansville in southwestern Indiana.

VEDO provides energy delivery

services to approximately 312,000 natural gas customers near Dayton in west central Ohio. Vectren’s company-owned generation fleet represents 1,158 megawatts (MW)1 of unforced capacity (UCAP) as shown in Table 1-1. Table 1-1 Generating Units Unit

UCAP (MW)

Primary fuel

Commercial Date

Northeast 1

9 MW

Gas

1963

Northeast 2

9 MW

Gas

1964

FB Culley 2

83 MW

Coal

1966

Warrick 4

135 MW

Coal

1970

FB Culley 3

257 MW

Coal

1973

AB Brown 1

228 MW

Coal

1979

BAGS 2

59 MW

Gas

1981

AB Brown 2

233 MW

Coal

1986

AB Brown 3

73 MW

Gas

1991

AB Brown 4

69 MW

Gas

2002

Blackfoot

3 MW

Landfill Gas

2009

1

Blackfoot landfill gas project is considered behind-the-meter and is therefore currently accounted for as a reduction to load and is omitted from the capacity total

November 2014 Page 19

2014 Integrated Resource Plan

In addition to company owned generating resources, Vectren has access to an additional 30 MW of capacity as a result of its 1.5% ownership interest in Ohio Valley Electric Corporation (OVEC). Vectren is also contracted to receive 80 MW of nominal capacity wind energy through two separate long-term purchase power agreements. The total firm capacity credit for the MISO 2014-2015 planning year for these wind resources is 7.3 MW. Vectren is interconnected with other utilities at both 345 kV and 138 kV and is able to exchange capacity and energy through the market mechanisms of the Midcontinent Independent System Operator (MISO). THE IRP PROCESS The Integrated Resource Plan (IRP) process was developed to assure a systematic and comprehensive planning process that produces a reliable, efficient approach to securing future resources to meet the energy needs of the utility and its customers. The IRP process encompasses an assessment of a range of feasible supply-side and demandside alternatives to establish a diverse portfolio of options to effectively meet future generation needs. In Indiana, the IRP is also guided by rules of the Indiana Utility Regulatory Commission (IURC). Those rules, found in the Indiana Administrative Code at 170 I.A.C. 4-7-4 through 4-7-9, provide specific guidelines for plan contents and filing with the Commission. On October 14, 2010, the IURC issued an order to commence rulemaking to revise/update the current Indiana IRP rule.

The following summer, Vectren

participated in a stakeholder process to provide input on updating the rule. proposed draft rule was sent to stakeholders on October 4, 2012.

The

Although not

finalized, Vectren voluntarily followed the proposed draft rule, which is found in the IRP Proposed Draft Rule Requirements Cross Reference Table of this IRP. Vectren modified its processes to meet the proposed draft rule. Most notably, Vectren incorporated a stakeholder process to gather input from stakeholders and answer stakeholder questions in an open, transparent process. The proposed rule requires at November 2014 Page 20

2014 Integrated Resource Plan

least 2 meetings with stakeholders. On March 20, 2014, Vectren met with stakeholders to discuss the base inputs of the plan, educate stakeholders on IRP related topics, and review the Vectren process. Based on feedback from stakeholders, Vectren added an additional meeting on August 5, 2014 to further discuss major assumptions and data inputs prior to modeling. Finally, on September 24, 2014 Vectren presented a preview of the plan.

A summary of the stakeholder meetings can be found in Chapter 2

Planning Process, and the meeting presentations and Q&A summaries are found in the Technical Appendix, section A. Details of the process used by Vectren to develop the recommended plan in this IRP are found in chapters 2 through 11 of this report. Chapter 11 Action Plan sets forth the action plan for Vectren over the next three years to achieve the long-term resource objectives described in this IRP. Included in the process is an updated demand and energy forecast (detailed in Chapter 5 Sales and Demand Forecast). Table 1–2, shows a summary of the demand and energy forecast. VECTREN’S QUANTITATIVE AND QUALITATIVE IRP PROCESS Historically, Vectren has used modeling to perform the evaluations, screenings, and assessments of various potential scenarios to arrive at a single plan that represented its “Resource Plan Additions.” Vectren continues to use the Strategist modeling software from Ventyx, as it has in its last several IRP studies. This software has traditionally been used by some of the other Indiana utilities, as well. The submitted plan was the result of a process that was primarily a quantitative evaluation performed using an industry standard planning model. The modeling performed by Vectren provides important information to evaluate future resource needs. However, Vectren will also continue to monitor developments that

November 2014 Page 21

2014 Integrated Resource Plan

could impact future resource needs.

Three developments that Vectren is focusing on

for impacts on the near term are: 1. The Clean Power Plan from the Environmental Protection Agency (EPA) and Indiana’s approach to implementing this rule. 2. MISO capacity market constraints resulting from the early retirements of coal units as a response to the EPAs MATS rule. 3. The impacts on Vectren’s load due to the addition of or loss of large customer load. While Vectren’s models attempt to evaluate the impact those issues may have on its future load, significant uncertainty remains. Vectren must maintain flexibility to adjust its plans based on the outcome of these and other unknown factors.

In the case of

Vectren, one of the smallest investor-owned electric utilities in the nation, the ramifications of major capacity decisions are particularly important. Equally important, Vectren believes one of the major objectives of the Commission’s reporting and filing requirements regarding the IRP process is to communicate with the IURC regarding the decision processes, evaluations, and judgments that Vectren uses to assist in making the resource planning decisions that are in the long-term best interest of Vectren’s customers and the communities it serves. Vectren understands that the action plan which results from the IRP process is to be used as a guide by the Company and the IURC in addressing long-term resource needs, as both attempt to carry out their respective responsibilities in the most effective manner possible. CHANGES SINCE LAST IRP While a number of changes have occurred since Vectren’s last IRP, four specific changes have had a significant impact on this IRP. First, the IURC’s proposed draft IRP rules were released after Vectren’s last IRP. Vectren is voluntarily following the new proposed draft IRP rule, which includes a stakeholder process, non-technical summary, more robust risk analysis, and attending an annual contemporary issues meeting in Indianapolis. The IRP Proposed Draft Rule Requirements Cross Reference Table on November 2014 Page 22

2014 Integrated Resource Plan

page three shows the new proposed draft rule and where Vectren addresses each part in this IRP. Second, Vectren engaged a third party consultant with significant experience conducting IRPs for other parties, Burns & McDonnell, one of the leading engineering design experts in the United States, to aid its preparation of this IRP. For the 2014 IRP, Vectren worked closely with Burns and McDonnell to perform Strategist modeling (including additional DSM modeling).

Burns and McDonnell has a great deal of

experience in working with companies across the country on resource modeling. They also performed the Technology Assessment, detailing costs for potential resource options. The Technology Assessment can be found in the Technical Appendix, section B. Third, the EPA has finalized various federal mandates with respect to further environmental regulation of Vectren’s generating units and proposed a sweeping greenhouse gas regulation for existing coal-fired generating sources since Vectren’s last IRP. As will be discussed in more detail in Chapter 4 Environmental, the EPA finalized its Mercury and Air Toxics Standard (MATS) in 2012, which set first ever plantwide emission limits for mercury and other hazardous air pollutants and has a compliance deadline of April 2015.

MATS has resulted in many announcements of

coal plant retirements across the US.

As a result, MISO, Vectren’s Regional

Transmission Operator (RTO), is predicting potential capacity shortfalls in the next few years.

In the next two years Vectren intends to spend $70- $90 million on its

environmental compliance program to meet not only the MATS rule, but also recent water discharge limits for mercury contained in water discharge permit renewals and mitigate incremental sulfur trioxide (SO3) emissions resulting from the installation of Vectren’s selective catalytic reduction technology under an agreement with the EPA. However, Vectren is projecting to defer recovery of these federally mandated costs until approximately 2020.

The assumptions in the IRP are consistent with Vectren’s

environmental compliance filing. November 2014 Page 23

2014 Integrated Resource Plan

In addition to the federal mandates referenced above, the EPA released its final rule regulating cooling water structures under Section 316(b) of the Clean Water Act (CWA) on August 15, 2014. Section 316(b) requires that intake structures that withdraw > 2 Million Gallons per Day (MGD) of water, including most electric generating units, use the "Best Technology Available" to prevent and / or mitigate adverse environmental impacts to shellfish, fish, and wildlife in a water body. This rule applies only to the FB Culley plant, as the AB Brown plant already utilizes cooling water towers. Finally, on June 2, 2014, the EPA issued the Clean Air Act Section 111(d) Greenhouse Gas (GHG) New Source Performance Standards (NSPS) for existing sources, known as the Clean Power Plan (CPP).

The CPP sets state-specific carbon reduction goals

based on a state’s existing generation mix based upon a building block approach and provides guidelines for the development, submission and implementation of state plans to achieve the state goals.

As yet, there is little clarity on how the state of Indiana will

choose to implement this rule. However, this IRP considers several of the potential building blocks in its assumptions: Demand Side Management (DSM), a potential renewables portfolio standard, and a price for carbon price beginning in 2020. Fourth, the Indiana General Assembly passed legislation in March of 2014 that modified DSM requirements in Indiana. Senate Enrolled Act No. 340 (“SEA 340”) removed requirements for mandatory statewide “Core” DSM programs and energy savings goals effective December 31, 2014. SEA 340 also allows large Commercial and Industrial (C&I) customers who meet certain criteria to opt-out of participating in utility sponsored DSM programs. Vectren continues to support DSM related energy efficiency efforts as a fundamental part of the services that are provided to customers in order to help them manage their energy bills. Vectren believes that a cost effective level of DSM energy efficiency may be supported by policy considerations beyond the IRP’s focus on planning for future November 2014 Page 24

2014 Integrated Resource Plan

resources. Consistent with this belief, Vectren’s base sales forecast includes a base level of DSM at a targeted level of 1% eligible annual savings for 2015 – 2019 and 0.5% annually thereafter for customer load that has not opted-out of DSM programs. Vectren also modeled whether incremental DSM energy efficiency programs would be selected as a resource when competing with supply side options, to meet future electric requirements.

Vectren’s approach attempts to balance its commitment to a level of

cost-effective DSM to help customers manage their energy bills, while evaluating additional DSM resources consistent with least cost planning. Note that since the last IRP was performed, Broadway Unit 1 (BAGS 1) has quit performing up to specifications. The unit has been on a long-term outage. Therefore, Vectren currently does not get credit for the unforced capacity (UCAP) amount, and it was not included in the analysis as shown in Table 1-1. BAGS 1 is a natural gas peaking unit, and in the past was typically good for approximately 40 MW on a UCAP basis. PLAN RESULTS / RECOMMENDATIONS The IRP indicates that Vectren does not need any incremental generation resources or purchase power agreements during the planning horizon. Although the IRP does not project incremental resource needs, Vectren proposes to continue offering DSM programs to help customers use less energy, thus lowering their total bill. The IRP forecasts that there may be some marginal economic benefit to retiring FB Culley 2 in 2020 under certain scenarios. This retirement evaluation is influenced by Vectren’s load forecast, carbon costs, and fuel costs. Vectren will continue to evaluate the impact of these components on Culley Unit 2 in successive IRPs to evaluate the optimal time to retire Culley Unit 2. As mentioned above and discussed in further detail in this IRP, the decision to retire FB Culley 2 will not be made until major near term uncertainties become more clear, most November 2014 Page 25

2014 Integrated Resource Plan

notably how the state of Indiana will implement the EPA’s Clean Power Plan (if the plan survives legal challenges).

Additionally, Vectren is actively working to attract new

industrial customers through economic development activities in southwestern Indiana. If a large customer chooses to locate within the Vectren electric service area, Culley 2 will be required to operate at least in the short term to provide the resources necessary to serve such a customer.

Leaving Culley Unit 2 in operation at this time provides

Vectren maximum flexibility to adapt to such future developments. Economic modeling does not necessarily account for all such developments that are very possible, and therefore, judgment must also be part of the analysis. Table 1-2 shows the peak and energy forecast.

Table 1-3 shows that no capacity additions are currently deemed

necessary. Vectren’s base case scenario assumptions are detailed in Chapter 10 Generation Planning. In summary, Vectren assumed a minimum planning margin of 7.3%1 for each year of the study.

Energy savings goals of 1% of eligible customer load were

incorporated into the load forecast through 2019.

Additionally, incremental energy

savings of .5% per year were assumed beginning in 2020 and were carried throughout the rest of the planning period. All assumptions are discussed in depth throughout this IRP. Sensitivity risk analyses were performed around coal, gas, energy, and carbon pricing, capital costs, and high environmental regulation cost.

These results are shown in

Chapter 10 Generation Planning. CONCLUSION Vectren recognizes that the electric utility industry is experiencing a fast-changing time in terms of potential regulations, environmental mandates, and technology advances. Given the significant impact of any resource decision on both customers and other stakeholders, Vectren will continue to actively monitor developments in the regulatory, 1

MISO unforced capacity (UCAP) requirement, further discussed in Chapter 3 MISO

November 2014 Page 26

2014 Integrated Resource Plan

environmental, and technology arenas for both their impact on future generation needs and existing facilities. Open communication with the IURC and other parties including the OUCC will be key to Vectren’s ability to make the best decisions for all stakeholders. Table 1-2 Peak and Energy Forecast Year

1

Annual Energy (GWh)

2014 Proj.

1,145

5,782

2015

1,155

5,914

2016

1,156

5,936

2017

1,113

5,514

2018

1,109

5,503

2019

1,106

5,494

2020

1,106

5,497

2021

1,106

5,492

2022

1,107

5,494

2023

1,107

5,494

2024

1,107

5,496

2025

1,106

5,487

2026

1,106

5,487

2027

1,107

5,492

2028

1,109

5,507

2029

1,110

5,509

2030

1,111

5,517

2031

1,111

5,523

2032

1,113

5,540

2033

1,114

5,548

2034

1,115

5,560

-0.1%

-0.2%

Compound Annual Growth Rate, 2014-2034

1

Peak (MW)

Includes wholesale contract sales for 2014

November 2014 Page 27

2014 Integrated Resource Plan

Table 1-3 Base Case Resource Plan

1 2

Year

Firm Peak 1 Demand (MW)

UCAP Company Owned Generation (MW)

DLC (MW)

2015

1,155

1,155

2016

1,156

2017

Interruptible (MW)

UCAP Committed Purchases (MW)

17

50

38

1,260

9.1%

1,155

17

50

38

1,260

9.0%

1,113

1,155

18

27

38

1,238

11.2%

2018

1,109

1,155

18

27

38

1,238

11.6%

2019

1,106

1,155

17

28

38

1,238

11.9%

2020

1,106

1,155

17

28

38

1,238

11.9%

2021

1,106

1,155

17

28

38

1,238

11.9%

2022

1,107

1,155

17

28

38

1,238

11.8%

2023

1,107

1,155

17

28

38

1,238

11.8%

2024

1,107

1,155

17

28

38

1,238

11.8%

2025

1,106

1,155

17

28

38

1,238

11.9%

2026

1,106

1,155

17

28

38

1,238

11.9%

2027

1,107

1,155

17

28

38

1,238

11.8%

2028

1,109

1,155

17

28

38

1,238

11.6%

2029

1,110

1,155

17

28

38

1,238

11.5%

2030

1,111

1,155

17

28

38

1,238

11.4%

2031

1,111

1,155

17

28

38

1,238

11.4%

2032

1,113

1,155

17

28

38

1,238

11.2%

2033

1,114

1,155

17

28

38

1,238

11.1%

2034

1,115

1,155

17

28

38

1,238

11.0%

Capacity Additions (MW)

Total Resources (MW)

Reserve Margin (%)2

Vectren is not forecasting firm wholesale contracts throughout this forecast. MISO requires a 7.3% Planning Reserve

November 2014 Page 28

2014 Integrated Resource Plan

This page intentionally left blank for formatting purposes

November 2014 Page 29

2014 Integrated Resource Plan

CHAPTER 2 PLANNING PROCESS

November 2014 Page 30

2014 Integrated Resource Plan

INTRODUCTION Vectren's IRP objectives are based on the need for a resource strategy that provides value to its customers, communities, and shareholders. In addition, this strategy must accommodate the ongoing changes and uncertainties in the competitive and regulated markets. Specifically, Vectren's IRP objectives are as follows: 

Provide all customers with a reliable supply of energy at the least cost reasonably possible

Develop a plan with the flexibility to rapidly adapt to changes in the market while minimizing risks

Provide high-quality, customer-oriented services which enhance customer value

Minimize impacts of Vectren’s past and current operations on local environments

PLANNING PROCESS The planning process is driven by the characteristics of Vectren's markets and the needs of its customers. These elements serve to define the utility's objectives and help establish a long-term forecast of energy and demand. Using the forecast as a baseline, the IRP process entails evaluation of both supply-side and demand-side options designed to address the forecast. These options serve as input into a formal integration process that determines the benefits and costs of various combinations of supply-side and demand-side resources. Because the IRP modeling process requires significant amounts of data and assumptions from a variety of sources, a process is needed to develop appropriate inputs to the models. The process criteria for inputs include: 

Maintain consistency in developing key assumptions across all IRP components

Incorporate realistic estimates based on up-to-date documentation with appropriate vendors and available market information, as well as internal departments

November 2014 Page 31

2014 Integrated Resource Plan

Consideration of impacts and experiences gained in prior IRP processes and demand-side program efforts

Vectren follows an integrated resource plan process that is very similar to other utilities throughout the country. In order to stay current with IRP methodologies and techniques, Vectren works with consultants, attends integrated resource planning conferences, and attends the annual contemporary issues meeting (hosted by the IURC). The diagram below illustrates the general process.

Identify objectives, metrics and risk perspectives Establish baseline and alternative future assumptions Determine resource options Identify ideal portfolios under various alternative futures (Scenarios) Expose portfolios to sensitivities and evaluate other risks Select “best” portfolios

Portfolio recommendations consistent with objectives

Vectren’s objective is to serve customers as reliably and economically as possible, while weighing future risks and uncertainties.

Vectren begins the process by

forecasting customers’ electric demand for 20 years. The electric demand forecast considers historical electric demand, economics, weather, appliance efficiency trends (driven by Federal codes and standards), population growth, adoption of customer owned generation (such as solar panels), and Vectren DSM energy efficiency programs (such as appliance rebates).

A base, low, and two high peak load forecasts were

developed.

November 2014 Page 32

2014 Integrated Resource Plan

The next step in the process is to determine possible alternative futures (scenarios) and determine how to reliably and economically meet customers’ future electric demand. Vectren has adequate resource options (power plants, on-going energy efficiency and demand response options) to meet customers’ need.

The base scenario assumes

customer need will be met with existing resources. The second scenario examines the potential impact of retiring FB Culley 2, Vectren’s oldest, smallest (83 MW), and most inefficient coal generating unit.

Additionally, it is not controlled for NOx.

The final

scenario included a possible future where the government enacts a Renewable Portfolio Standard (RPS), requiring 20% of electricity to be produced with renewable resources, such as wind, solar, customer-owned renewable distributed generation, and utility sponsored DSM energy efficiency programs. Each electric demand forecast is exposed to the base and two alternate futures to determine the most economical way to meet customer needs, resulting in 12 possible plans. The diagram below illustrates each alternative.1

1

1

Base Demand Forecast

2

Low Demand Forecast

3

High (modeled) Demand Forecast

4

High (large load) Forecast1

A

B

C

Base

FB Culley 2 Unit Retirement

RPS

The base demand forecast with a 100 MW firm load addition in 2018

November 2014 Page 33

2014 Integrated Resource Plan

Each plan represents the lowest-cost option to meet customer demand.

Several

resource options were considered in the analysis to meet customer demand, including various (types and sizes) natural gas powered generation options, additional energy efficiency programs beyond what is already included in the electric demand forecasts, renewables (wind and solar generation), and short-term market capacity purchases. All model inputs and assumptions are loaded into a modeling tool called Strategist, which is used by many utilities throughout the country. The modeling tool optimizes for the lowest-cost plan to meet customer demand, plus a 7.3% UCAP planning reserve margin. Each plan was then subjected to additional risk sensitivities to determine which plan is the lowest cost over a wide range of possible future risks. As previously mentioned, resource modeling requires a large number on inputs and assumptions: forecasts for natural gas prices, coal prices, market energy prices, CO2 prices, costs of resource options, and potential costs for regulations. If the costs of any of these risk factors vary significantly from the base forecasts, the results of the analysis could potentially be different. Each plan (A1-C4) was subjected to varying costs (most often +/- 20%) for the risk factors mentioned above to determine the impact to each plan from the possible future sensitivities.

November 2014 Page 34

2014 Integrated Resource Plan

The remainder of this IRP is organized as follows: MISO Chapter 3 -

Discusses Vectren’s participation in MISO and the implications for resource planning

Environmental Chapter 4 - Discusses current and pending environmental issues and regulations and the potential considerations for resource decisions Forecast Chapter 5 - Contains the electric sales and demand forecast Supply-Side Chapter 6 - Describes the electric supply analysis including a review and screening of the various electric supply options Chapter 7 - Describes the viability and application of renewable and clean energy technologies and renewable energy credits (RECs) Chapter 9 - Contains a discussion of Vectren's transmission and distribution expansion plan forecast Demand-Side Chapter 8 - Presents a discussion of DSM resources including screening results and program concept development Integration Chapter 10 - Details the formal integration process which includes conducting sensitivity analyses and obtaining the final resource plan Short term Action Plan Chapter 11 - Contains action plans designed to implement the resource plan over the next three years

November 2014 Page 35

2014 Integrated Resource Plan

This page intentionally left blank for formatting purposes

November 2014 Page 36

2014 Integrated Resource Plan

CHAPTER 3 MISO

November 2014 Page 37

2014 Integrated Resource Plan

INTRODUCTION Vectren was an original signer of the Transmission Owners Agreement, which organized the Midwest Independent Transmission System Operator, now known as the Midcontinent Independent System Operator (MISO) and under which authority the MISO administers its Open Access Transmission, Energy and Operating Reserve Markets Tariff (MISO Tariff). As a vertically integrated utility with the responsibility and obligation for serving load within the MISO footprint, Vectren has integrated many functions with the operating procedures of MISO.

This integration involves the

coordinated operation of its transmission system and generating units, and the functions range from owning and operating generation and transmission, to complying with certain reliability standards.

These standards include planning and operation of

resources to meet the needs of loads in the future and are set by the North American Electric Reliability Corporation (NERC) and the regional reliability entity Reliability First Corporation, both of which are overseen by the Federal Energy Regulatory Commission (FERC). MISO OVERVIEW MISO, headquartered in Carmel, Indiana, with additional offices in Egan, Minnesota, was approved as the nation's first regional transmission organization in 2001. Today, MISO manages one of the world’s largest energy and operating reserves markets; the market generation capacity was 175,436 MW as of May 1, 2014. This market operates in 15 states and one Canadian province.

November 2014 Page 38

2014 Integrated Resource Plan

Key Dates 

February 1, 2002 - Transmission service began under MISO Open-Access Transmission Tariff with Vectren as a full Transmission Owning Member

April 1, 2005 - Midwest markets launch

April 16, 2008 - NERC certified MISO as Balancing Authority

January 6, 2009 - Ancillary Services Markets began and MISO became the region’s Balancing Authority

December 19, 2013 – Added South Region

Vectren in Relation to MISO Footprint With a native peak load of about 1,150 MW, Vectren is approximately 1.4% of the MISO market footprint and is one of 36 local balancing authorities. In addition, the Vectren transmission system supports multiple municipals and a large industrial smelter. The total control area or Local Balancing Area (LBA) is approximately 1,900 MW. Figure 3-1 below is a drawing of the entire MISO market footprint, and Figure 3-2 shows the MISO Reliability Coordination Area. Figure 3-1 MISO Market Area

Vectren Service Territory

November 2014 Page 39

2014 Integrated Resource Plan

Figure 3-2 MISO Reliability Coordination Area MISO’s GOALS The goal of MISO’s regional transmission planning process is

the

development

comprehensive

of

a

expansion

plan that meets both reliability and

economic

expansion

needs. This process identifies solutions for reliability issues that arise from the expected dispatch of network resources. These evaluating

solutions alternative

include costs

between capital expenditures for transmission expansion projects and increased operating expenses from redispatching network resources or other operational actions. The MISO Board of Directors has adopted six planning principles to guide the MISO regional plan: 1. Make the benefits of an economically efficient energy market available to customers by identifying transmission projects which provide access to electricity at the lowest total electric system costs. 2. Provide a transmission infrastructure that upholds all applicable NERC and Transmission Owner planning criteria and safeguards local and regional reliability through identification of transmission projects to meet those needs. 3. Support state and federal energy policy requirements by planning for access to a changing resource mix.

November 2014 Page 40

2014 Integrated Resource Plan

4. Provide an appropriate cost allocation mechanism that ensures the costs of transmission projects are allocated in a manner roughly commensurate with the projected benefits of those projects. 5. Analyze system scenarios and make the results available to state and federal energy policymakers and other stakeholders to provide context and to inform choices they face. 6. Coordinate transmission planning with neighboring planning regions to seek more efficient and cost-effective solutions.1 MISO is designated as Vectren’s Planning Authority, under the NERC reliability standards, and in FERC Order 1000, MISO has additional regional planning responsibilities. MISO PLANNING PROCESS MISO Transmission Planning Process MISO’s transmission planning process begins with the models for the current planning cycle and includes opportunities for stakeholder input on the integration of transmission service requests, generator interconnection requests, and other studies to contribute to the development of an annual MISO Transmission Expansion Plan (MTEP) report. The 2013 MTEP recommended $1.48 billion in 317 new projects across the MISO footprint through the year 2023. MISO MTEP process has recommended $17.9 billion total investment since its 2003 inception through the first 10 years.

1

These Guiding Principles were initially adopted by the Board of Directors, pursuant to the recommendation of the System Planning Committee, on August 18, 2005, and reaffirmed by the System Planning Committee in February 2007, August 2009, May 2011, and March 2013.

November 2014 Page 41

2014 Integrated Resource Plan

MISO’s role in meeting Vectren’s requirements as a member of ReliabilityFirst for a Planning Reserve Margin As a result of the Energy Policy Act of 2005, regional entities were delegated authority by FERC to establish standards to provide for reliable operation of the bulk-power system. Vectren is a member of regional entity ReliabilityFirst, and so must comply with regional entity Reliability First standards, including the Planning Resource Adequacy Analysis and the Assessment and Documentation Standard BAL-502-RFC-02. This assessment and documentation standard requires planning coordinators to perform annual resource adequacy analyses.

This includes calculating a planning reserve

margin (PRM) that will result in the sum of the probabilities for loss of load for the integrated peak hour for all days of each planning year equal to a one day in 10 year criterion.

This PRM requirement also includes documenting the projected load,

resource capability, and PRM for the years under study, and other particular criteria. The first planning year the Reliability First Planning Reserve Standard was in effect (June 2008-May 2009), Vectren complied with the ReliabilityFirst Planning Resource Adequacy standard by participating in the Midwest Planning Reserve Sharing Group. The calculated required PRM for Vectren was 14.3% on an installed capacity basis. For planning year June 2009-May 2010 and beyond, Vectren and all other MISO utilities have delegated their tasks assigned to the Load Serving Entities (LSEs) under BAL502-RFC-02 to MISO. The specific section of the MISO Tariff that addresses planning reserves is Module E-1 Resource Adequacy.

Vectren is complying with the

ReliabilityFirst Planning Resource Adequacy standard by meeting the MISO Module E individual LSE required PRM. This PRM (UCAP) is 7.3% for planning year June 2014 May 2015. MISO’s Module E-1 As previously mentioned, Module E-1- Resource Adequacy is the portion of the MISO Tariff which requires MISO to determine the Planning Reserve Margin Requirement, on November 2014 Page 42

2014 Integrated Resource Plan

an unforced capacity (UCAP) basis, that would result in 1 day in 10 Loss of Load Event reliability standard. Module E-1 and its associated business practice manual lays out the mandatory requirements to ensure access to deliverable, reliable and adequate planning resources to meet peak demand requirements on the transmission system. To perform these calculations, MISO requires entities to utilize their Module E Capacity Tracking Tool (MECT) to submit a forecast of demand and list their qualified resources. This same tool is then leveraged to accept offers into MISO’s annual Planning Resource Auction (PRA). Loss of Load Expectation and Determination of Planning Reserve Margins MISO used a Loss of Load Expectation1 (LOLE) of 1 day in 10 years as the probabilistic method to determine expected number of days per year for which available generating capacity is insufficient to serve the daily peak demand (load). This LOLE, along with other LSE-specific data, is used to perform a technical analysis on an annual basis to establish the PRM UCAP for each LSE. The PRM analysis considers other factors such as generator forced outage rates of capacity resources, generator planned outages, expected performance of load modifying resources, forecasting uncertainty, and system operating reserve requirements. For this year, an unforced capacity planning reserve margin of 7.3% applied to the MISO system Coincident Peak Demand has been established for the planning year of June 2014 through May 2015. This value was determined by MISO through the use of the GE Multi-Area Reliability Simulation (MARS) software for Loss of Load analysis. Effect of Load Diversity Within Module E-1, individual LSEs maintain reserves based on their Coincident Peak Demand, which is the LSE’s demand at the time of the MISO peak. MISO no longer calculates a Load Diversity Factor for LSE’s, as this would be different for each LSE. However, each LSE peaks at a different time, and for reference, an LSE can determine 1

Included in the Technical Appendix, section I

November 2014 Page 43

2014 Integrated Resource Plan

what the PRM UCAP would be when accounting for load diversity by multiplying the PRM UCAP times the ratio of LSE Coincident Peak Demand divided by LSE peak Demand. Forecast LSE Requirements LSEs must demonstrate that sufficient planning resources are allocated to meet the LSE Coincident Peak Demand multiplied by one plus the PRM and one plus transmission losses.

The submission of this forecast follows MISO’s prescribed

processes. LSEs must report their peak demand forecasts for each month of the next two planning years and for each summer period (May-October) and winter period (November-April) for an additional eight (8) planning years for the NERC MOD standards. Forecasted demand in MISO reflects the expected “50/50” LSE Coincident Peak Demand and includes the effect of all distribution and transmission losses. This means there is a 50% chance that actual demand will be higher and a 50% chance that actual demand will be lower than the forecasted level. LSEs must also report their Net Energy for Forecasted Demand for the same time periods: monthly for the next two planning years and for each summer period (MayOctober) and winter period (November-April) for an additional eight (8) planning years for the NERC MOD standards. LSEs register demand side management into the MECT tool separate from their demand forecasts.

These resources are explicitly modeled on the supply side in

determination of the PRM.

November 2014 Page 44

2014 Integrated Resource Plan

Resource Plan Requirements LSEs are obligated to provide MISO with resource plans demonstrating that Zonal Resource Credits (ZRC) will be available to meet their resource adequacy requirements. Generally, the Planning Reserve Margin Requirement (PRMR) is the forecast LSE Peak Demand multiplied by one plus MISO PRM UCAP and one plus transmission losses, unless the state utility commission establishes a PRM that is different from MISO’s.

Additionally LSEs must meet a Local Clearing Requirement

(LCR) for the Local Resource Zone (LRZ) for which the LSE resides, Vectren is in LRZ six. The LCR is equal to the Local Reliability Requirement (LRR) less the Capacity Import Limit (CIL) into that zone. The LRR is established so that the LRZ can also meet the 1 day in 10 LOLE reliability standard by clearing the necessary resources within the LRZ. If a state utility commission establishes a minimum PRM for the LSEs under their jurisdiction, that state-set PRM will be adopted by MISO for affected LSEs in such state. If a state utility commission establishes a PRM that is higher than the MISO established PRM, the affected LSE’s must meet the state-set PRM.1 Indiana does not have a stated minimum planning reserve margin; therefore, Vectren must meet the PRM of MISO. Qualification of Resources, Including Unforced Capacity Ratings (UCAP), Conversion of UCAP MW to Zonal Resource Credits To comply with MISO Resource Adequacy provisions, LSEs must submit data for their eligible resources for MISO to determine the total installed capacity that the resource can reliably provide, called Unforced Capacity Rating (UCAP).

1

From MISO BPM-011-r13 Resource Adequacy Section 3.5.5 State Authority to set PRM

November 2014 Page 45

2014 Integrated Resource Plan

MISO will calculate unforced capacity for all generation resources interconnected to the MISO Transmission System while respecting the interconnection study results and the results of the aggregate deliverability analysis. The first step is to compare a Generation Resource Net Dependable Capacity (NDC) to the tested capacity from the interconnection process to determine the total installed capacity that the generation resource can reliably provide, which is the Total Interconnection Installed Capacity (ICAP). A unit’s NDC for the Planning Year is determined by averaging the NDC data that is entered into MISO’s Generating Availability Data System (GADS) database. The UCAP rating represents the MW’s that are eligible to be converted into ZRCs. Evaluation and Reporting MISO will maintain databases and will “..provide to states, upon request, with relevant resource adequacy information as available…” per section 69 of the MISO Tariff during relevant time periods, subject to the data confidentiality provisions in section 38.9 of the MISO Tariff. Vectren’s approach to the Voluntary Capacity Auction Due to the long lead time generally required to build capacity resources, Vectren does not consider MISO’s annual Planning Resource Auction an appropriate means to meet the needs of the 20 year Integrated Resource Plan and continues to pursue more traditional means of ensuring adequate resources. Future of MISO’s Module E MISO proposed Capacity Market MISO is currently evaluating whether the annual summer based resource adequacy construct contains gaps that prevent it from achieving resource adequacy during all periods of the year. MISO is working to identify seasonal or other changes that will close any identified gaps. November 2014 Page 46

2014 Integrated Resource Plan

Footprint Changes On Dec. 19, 2013 MISO began coordinating all RTO activities in the newly combined footprint consisting of all or parts of 15 states with the integration of the MISO south entities which include the LBAs of Entergy Arkansas, Inc., Entergy Texas, Inc., Entergy Mississippi, Inc., Entergy Louisiana, LLC, Entergy Gulf States Louisiana, L.L.C., Entergy New Orleans, Inc., Cleco Power LLC, Lafayette Utilities System, Louisiana Energy & Power Authority, South Mississippi Electric Power Authority and Louisiana Generating, LLC. DEMAND RESPONSE Demand response is an integral part of a utility’s system, operations, and planning, and helps Vectren meet the obligation to serve all customers. Effective July 1, 2011 and pursuant to Commission order in Cause 34566 MISO 4, Vectren filed Rider DR, which provides qualifying customers the optional opportunity to reduce their electric costs by participating in the MISO wholesale energy market. This rider helps the Company’s efforts to preserve reliable electric service through customer provision of a load reduction during MISO high price periods and declared emergency events. This initial Rider DR offers two programs, Emergency Demand Response (EDR) and Demand Response Resource Type 1 (“DRR-1”) energy programs. MISO FORECAST Based on analysis of load forecasts and planned resources derived from survey responses provided by the load serving entities in its footprint, MISO has created several iterations of resource adequacy forecasts that indicate beginning in 2016, several zones within the footprint may lack the capacity required to meet reserve requirements. MISO continues to assess the accuracy of this analysis and appears to concede that state regulatory commissions remain confident that adequate reserves exist in the near term. However, such studies do highlight the potential reliability issues created by the EPA emissions restrictions, and in particular, the potential for numerous base load coal plant retirements driven by the EPA’s Clean Power Plan. Questions November 2014 Page 47

2014 Integrated Resource Plan

regarding available capacity, as well as local reliability concerns will be factored into the Company's planning processes. Vectren’s Approach to Resource Adequacy Vectren will continue to comply with MISO’s Module E requirements, which includes the possibility for varying amounts of planning reserves.

November 2014 Page 48

2014 Integrated Resource Plan

This page intentionally left blank for formatting purposes

November 2014 Page 49

2014 Integrated Resource Plan

Chapter 4 ENVIRONMENTAL

November 2014 Page 50

2014 Integrated Resource Plan

INTRODUCTION Compliance planning associated with existing and anticipated environmental laws and regulations in each of the three media (air, water and waste) is discussed in this chapter. CURRENT ENVIRONMENTAL COMPLIANCE PROGRAMS: AIR Acid Rain Program Vectren's Acid Rain compliance program was approved by the IURC in Cause No. 39347, which authorized the construction of a combined sulfur dioxide (SO2) scrubber for FB Culley Units 2 and 3. As AB Brown Units 1 and 2 were newer vintage units, the units' original construction included scrubber technology.

Vectren relies upon its

existing scrubber technology for compliance with acid rain requirements and has sufficient allowance allocations to meet its future acid rain obligations. See, Table 4-1, a listing of current air pollution control devices for each Vectren unit, Table 4-2, a listing of emission rates for each Vectren unit, and Table 4-3 a listing of the acid rain allowances allocated to Vectren units. Table 4-1 Air Pollution Control Devices Installed Commercial Date MW (UCAP) NOX SO2 PM3

FB Culley 2 1966 83 Low NOX Burner FGD2 ESP4

FB Culley 3 1973 257 SCR1 FGD FF5

Warrick 4 1970 135 SCR FGD ESP

AB Brown 1 1979 228 SCR FGD FF

AB Brown 2 1986 233 SCR FGD ESP

1

Selective Catalytic Reduction Flue Gas Desulfurization 3 Particulate Matter 4 Electrostatic Precipitator 5 Fabric Filter 2

November 2014 Page 51

2014 Integrated Resource Plan

Table 4-2 Current (2013) Emission Rates (lbs./mm Btu) SO2

Annual NOX

AB Brown 1

0.6400

0.1510

Ozone Season NOX 0.1464

AB Brown 2

0.3610

0.1160

0.1091

AB Brown 3

0.0006

0.1800

0.1710

AB Brown 4

0.0006

0.0310

0.0214

Units

FB Culley 2/3

0.1700

0.1190

0.1312

Warrick 4

0.1800

0.2400

0.2740

BAGS 2

0.0006

0.2226

0.2111

Table 4-3 SO2 Acid Rain Allowances Allocated to Vectren Units (per year) 2013

2014-2041

AB Brown

Percent Ownership 100%

10,546

10,546

FB Culley

100%

9,922

9,922

50%

5,122

5,122

Plant Name

1

Warrick 4

For purposes of compliance year 2014, acid rain allowances will continue to be used for compliance with the SO2 emission reductions requirements of the Clean Air Interstate Rule (CAIR). As detailed more fully below, the Cross-State Air Pollution Rule (CSAPR) which was originally slated to become effective in two phases during 2012 and 2014, was stayed by the Court in December 2011 and vacated in August 2012. Through a series of appeals, it was reviewed by the US Supreme Court who issued judgment on April 29, 2014 to reverse the lower Court decision and upheld CSAPR. The stay was lifted on October 23, 2014 but an implementation schedule and reallocation of allowances has not been determined at this time. Due to the timing of this recent decision, Vectren is unable to state when CSAPR will go into effect and what the final allowance levels will be for each of its units.

Neither the CAIR rule nor CSAPR

supersedes the Acid Rain program. Facilities will still be required to annually surrender acid rain allowances to cover emissions of SO2 under the existing Acid Rain program.

1

Number of allowances shown are for Vectren’s portion of Warrick 4

November 2014 Page 52

2014 Integrated Resource Plan

NOx SIP Call Vectren's NOx SIP Call compliance plan was approved by the IURC in Cause Nos. 41864 and 42248, which authorized Vectren to retrofit selective catalytic reduction (SCR) technology on Culley Unit 3, Warrick Unit 4, and Brown Units 1 and 2. Vectren relies upon its existing SCR technology for compliance with the seasonal NOx reductions required in the NOx SIP Call. When CAIR was finalized in March of 2005, the EPA included a seasonal NOx emission reduction requirement, which incorporated, and in most cases, went beyond the seasonal NOx emission reductions required under the NOx SIP Call.

For purposes of compliance year 2014, CAIR NOx seasonal

allowances will continue to be used for compliance with the seasonal NOx emission reductions requirement under the current CAIR rule. CAIR and CSAPR are discussed more fully below. CAIR and CSAPR On March 10, 2005, the US Environmental Protection Agency (EPA) finalized its determination in the CAIR rule that emissions from coal-burning Electric Generating Units (EGUs) in certain upwind states result in the transport of fine particles (PM2.5) and ozone that significantly contribute to nonattainment of the applicable ambient air quality standards for those pollutants in downwind states. The CAIR rule required revisions to state implementation plans in twenty eight states, including Indiana, requiring further reductions of NOx and SO2 from EGUs beyond those required in the NOx SIP Call and Acid Rain programs.

Emissions reductions under the CAIR rule were to be

implemented in two phases, with requirements for first phase reductions in 2009 (NOx) and 2010 (SO2), and second phase reductions starting in 2015. The Warrick 4 scrubber was constructed to comply with the CAIR regulation and approved in Cause No. 42861. The CAIR rule provided a federal framework for a regional cap and trade system, and those allowances allocated to the Vectren units under the CAIR rule are being used for compliance in 2014 and until the EPA reinstates CSAPR (see below).

November 2014 Page 53

2014 Integrated Resource Plan

On July 6, 2010, the EPA proposed its Clean Air Transport Rule ("Transport Rule") in response to the court's remand of CAIR. In an effort to address the court's finding that CAIR did not adequately ensure attainment of ozone and PM2.5 air quality standards in certain Eastern states due to unlimited trading and banking of allowances, the Transport Rule proposal dramatically reduced the ability of facilities to meet the required emission reductions through interstate allowance trading.

Like CAIR, the Transport Rule

proposal set individual state caps for SO2 and NOx; however, unlike CAIR, individual unit allowance allocations were set out directly in the Transport Rule proposal. Interstate allowance trading was severely restricted and limited to trading within a zonal group.

On July 7, 2011, the EPA finalized the Transport Rule proposal and renamed

the program the Cross State Air Pollution Rule (CSAPR).

CSAPR sets individual

allowance allocations for Vectren's units directly in the rule. Table 4-4 shows a listing of individual unit allowance allocations under the original CSAPR.

Under the original

version of CSAPR, any excess CAIR allowances (vintage 2011 or older) that were not needed for compliance in 2011 could not be used for compliance with CSAPR, which was scheduled to become effective January 1, 2012. It is not yet known how, or when, the EPA will revise the effective dates in the reinstated version of the rule. Given the stringent state emission caps, the limited allowance trading available under the CSAPR, and the unknown implementation timing due to the recent lifting of the court ordered stay on October 23, 2014 it is virtually impossible to predict with any certainty the availability of excess allowances for compliance and the costs of those allowances under a reinstated CSAPR.

November 2014 Page 54

2014 Integrated Resource Plan

Table 4-4 CSAPR Allowances Allocated to Vectren Units SO2 Allocation

Annual NOX

Seasonal NOX

2012

2014

2012

2014

2012

2014

AB Brown 1

3,761

2,080

1,393

1,376

595

586

AB Brown 2

3,889

2,151

1,440

1,422

601

591

AB Brown 3

1

1

19

19

14

14

AB Brown 4

6

6

4

4

BAGS 2

26

26

18

8

FB Culley 2

1,488

925

619

612

268

264

FB Culley 3

2,923

2,799

1,874

1,851

792

780

Warrick 4

2,802

1,550

1,037

1,025

444

437

Vectren's original multi-pollutant compliance plan was approved under IURC Cause No. 42861. While Vectren's original multi-pollutant planning focused on compliance with the CAIR regulation which was in place at the time, the successful execution of the approved multi-pollutant plan would enable Vectren to comply with the SO2 and NOx emission caps in the original CSAPR allocation without further significant capital investment; however, while currently well controlled, Vectren will incur increased Operating and Maintenance (O&M) costs attributable to a new regulation, such as an increase in chemical costs to achieve the lower emission targets. With the completion of the Warrick 4 scrubber pursuant to the approved order in Vectren's multi-pollutant proceeding, Vectren's generating system is 100% scrubbed for SO2 and has selective catalytic reduction technology on all but one unit (FB Culley Unit 2). See Table 4-1. As such, Vectren will be well-positioned to comply with the new, more stringent SO2 and NOx caps that are required by a re-instated CSAPR, without reliance on a highly uncertain allowance market or further significant capital expenditures. It is important to note that CSAPR stay was just recently lifted on October 23, 2014, and final implementation dates are still unknown.

November 2014 Page 55

2014 Integrated Resource Plan

Mercury and Air Toxics Rule The 1990 Amendments to the Clean Air Act (CAA or Act) required that the EPA determine whether EGUs should be required to reduce hazardous air pollutants, including mercury, under § 112 of the Act. In December of 2000, the EPA officially listed coal-fired EGUs as subject to CAA § 112 Maximum Achievable Control Technology (MACT) Standards for mercury, thus lifting a previous exemption from the air toxics requirements. On March 15, 2005, the EPA finalized its Clean Air Mercury Rule (CAMR) which set "standards of performance" under CAA §111 for new and existing coal-fired EGUs and created a nation-wide mercury emission allowance cap and trade system for existing EGUs which sought to reduce utility emissions of mercury in two phases. The first phase cap would have started in 2010, except the CAMR rule was similarly vacated by a reviewing court in March of 2008. Thus, like the CAIR rule, utilities were preparing for compliance with a finalized CAMR regulation that was ultimately found to be deficient by a reviewing court. The reviewing court directed the EPA to proceed with a MACT rulemaking under CAA § 112 which would impose more stringent individual plant-wide limits on mercury emissions and not provide for allowance trading. On March 16, 2011, the EPA released its proposed MACT for utility boilers. The final rule, known as the Mercury and Air Toxics Standards (MATS) was published in the Federal Register on February 16, 2012. The rule sets plant-wide emission limits for the following hazardous air pollutants (HAPs): mercury, non-mercury HAPs (e.g. arsenic, chromium, cobalt, and selenium), and acid gases (hydrogen cyanide, hydrogen chloride, and hydrogen fluoride). The EPA established stringent plant-wide mercury emission limits (1.2 lb/TBtu for individual unit or 1.0 lb/TBtu for plant average) and set surrogate limits for non-mercury HAPs (total particulate matter limit of .03 lb/MMBtu) and acid gases (HCL limit of .002 lb/MMBtu). The surrogate limits can be used instead of individual limits for each HAP. Compliance with the new limits will be required by April 16, 2015. The Indiana Department of Environmental Management (IDEM), the state permitting authority, has the discretion to grant a compliance extension of up to November 2014 Page 56

2014 Integrated Resource Plan

one year on a case by case basis if a source is unable to install emission controls or make fuel conversions prior to the April 2015 deadline. Vectren was granted a 1-year extension for the AB Brown Unit 2, contingent upon the need for injection of a secondary mercury treatment chemical. The need for the secondary chemical will not be known until after the primary system is operational at the end of 2014. Vectren currently has a MATS Compliance plan before the Commission (IURC Cause 44446) for approval that includes organo sulfide injection at the baseload units (AB Brown 1, AB Brown 2, FB Culley 3, and Warrick 4) with the possibility of an additional HBr injection at AB Brown 2 if needed. SOLID WASTE DISPOSAL Scrubber by-products from AB Brown are sent to an on-site landfill permitted by IDEM. During the fall of 2009, Vectren finalized construction of a dry fly ash silo and barge loading facility that would allow for the beneficial reuse of Vectren generated fly ash. Since February 2010, the majority of AB Brown fly ash has been diverted to the new dry ash handling system and sent for beneficial reuse to a cement processing plant in St. Genevieve, Missouri, via a river barge loader and conveyor system. The remainder of the A B Brown fly ash and bottom ash is sluiced to an on-site pond.

This major

sustainability project will serve to mitigate negative impacts from the imposition of a more stringent regulatory scheme for ash disposal.

The majority of Vectren's coal

combustion materials are now being diverted from the existing ash pond structures and surface coal mine backfill operations and transported offsite for recycling into a cement application. Fly ash from the FB Culley facility is similarly transported off-site for beneficial reuse in cement. Until mid-2009, fly ash from the FB Culley facility was sent to the Cypress Creek Mine for backfill pursuant to the mine's surface coal mine permit. In May 2009, FB Culley began trucking fly ash to the St. Genevieve cement plant. Upon completion of the barge loading facility at the AB Brown facility in late 2009, FB Culley's fly ash is now transported to the AB Brown loading facility and shipped to the cement plant via November 2014 Page 57

2014 Integrated Resource Plan

river barge. The FB Culley facility sends its bottom ash to one of two on-site ponds via wet sluicing. The ponds are seven and eighteen acres in size. Scrubber by-product generated by the FB Culley facility is also used for beneficial reuse and shipped by river barge from FB Culley to a wallboard manufacturer.

In summary, the majority of

Vectren's coal combustion material is no longer handled on site, but is being recycled and shipped off-site for beneficial reuse. HAZARDOUS WASTE DISPOSAL Vectren’s AB Brown and FB Culley plants are episodic producers of hazardous waste that may include paints, parts washer fluids, or and other excess or outdated chemicals. Both facilities are typically classified as Conditionally Exempt Small Quantity Generators. WATER AB Brown and FB Culley currently discharges process and cooling water to the Ohio River under National Pollutant Discharge Elimination System (NPDES) water discharge permits issued by the IDEM. AB Brown utilizes cooling towers while FB Culley has a once through cooling water system. The Ohio River Valley Sanitation Commission (ORSANCO) regional water quality standards were most recently revised in 2012 and are more restrictive than current EPA standards. ORSANCO is a regional state compact focused on water quality issues for the Ohio River and governs water discharges that enter the Ohio River. Under Vectren’s most recent NPDES permits issued in late 2011, Vectren must meet more restrictive mercury limits at its river outfall to comply with the ORSANCO mercury limit of 12 ppt monthly average. To meet the limits, Vectren chose to install two chemical-precipitation water treatment systems at AB Brown and one at FB Culley. The new water treatment systems are included in the pending environmental compliance proceeding before the IURC (Cause No. 44446), and began operation in third quarter 2014.

November 2014 Page 58

2014 Integrated Resource Plan

FUTURE ENVIRONMENTAL REGULATIONS CARBON REGULATION On June 2, 2014, the EPA issued the CAA Section 111(d) Greenhouse Gas (GHG) New Source Performance Standards (NSPS) for existing sources, known as the Clean Power Plan (CPP). The CPP sets state-specific carbon reduction goals based on a state’s existing generation mix and provides guidelines for the development, submission and implementation of state plans to achieve the state goals. The EPA asserts that the state reduction goals will result in a 30% decrease in CO2 emissions from 2005 levels by 2030. To insure each state is making adequate progress towards the 2030 goal, an interim emission rate goal for 2020-2029 has also been established. Indiana’s state specific emission rate goals are 1,607 lb CO2/MWh for the interim period and 1,531 lb CO2/MWh for a final goal.

This equates to a 20% reduction in CO2

emission rates from 2012 levels. The EPA determined the state specific goals through a portfolio approach that includes improving power plant heat rates, dispatching lower emitting fuel sources more frequently and increasing utilization of renewable energy sources and energy efficiency programs. Specifically, each state’s goals were set by taking 2012 emissions data and applying four “building blocks” of emission rate improvements that the EPA has determined are achievable by that state. The four building blocks used by the EPA to calculate state goals are as follows: 1) Coal fleet heat rate improvement of 6%. 2) Increased dispatch of existing baseload natural gas generation sources to 70%. For Indiana this also includes announced new natural gas combined cycle plants. 3) Renewable energy portfolio of 5% in the interim and 7% in the final stage. 4) Energy efficiency reductions of 1.5% annually starting in 2020. While individual state goals were based on the EPA’s application of the building blocks to 2012 emission rates, states have flexibility through their state implementation plan to November 2014 Page 59

2014 Integrated Resource Plan

implement the building blocks in part or not at all to reach the listed goal, or enter a regional trading program. Since the state plan may include a variety of options, many of which are outside the fence line and control of a power plant, the interim and final CO2 emission rates will not necessarily apply to individual generating plants or companies within the state. It is yet to be determined how the CPP will directly affect Vectren’s generating units. The final rule is scheduled for June 2015, with individual state implementation plans due by June 2016. States have the option to seek a one year extension, or up to two years if part of a regional or multi-state plan. After the submittal of the state or regional plan, the first annual reporting begins in 2022. This timeline represents the earliest emission reductions will be required, as it is almost certain that this rule will be heavily litigated. Vectren will continue to work with the state of Indiana to ensure that the State’s compliance plan is the least cost to Indiana consumers. WASTE DISPOSAL Over the course of the last twenty years the EPA has conducted numerous studies and issued two reports to Congress on the management of coal combustion by-products (primarily fly ash, bottom ash, and scrubber by-product), concluding both times that these materials generally do not exhibit hazardous waste characteristics and can be managed properly under state solid waste regulations.

In response to the Tennessee

Valley Authority’s (TVA's) catastrophic ash pond spill in December of 2008, the EPA revisited its regulatory options for the management of coal combustion by-products. On June 21, 2010, the EPA published three options for a proposed rule covering Coal Combustion Residuals (CCRs). Two options would regulate combustion by-products as solid waste under the Resource Conservation and Recovery Act (RCRA) Subtitle D, with the only significant difference being whether existing ponds are retrofitted or closed within five years, or whether utilities will be permitted to continue to use an existing pond for its remaining useful life. The third option would regulate combustion by-products as hazardous waste under RCRA Subtitle C. Under all three options, certain beneficial reNovember 2014 Page 60

2014 Integrated Resource Plan

uses of coal combustion residuals, such as cement and wallboard applications, will continue to be allowed. The EPA has set December 19, 2014 as the deadline for issuing the final rule. Uncertainties remain until the rule is finalized.

For example, under the Subtitle D

proposed rule, unlined ash ponds would have to be closed within five years and groundwater monitoring installed within one year.

The proposal, however, did not

define whether the term “close” means to cease receiving new material or to have the site completely capped and grass covered within five years. The proposal also failed to take into account site specific circ*mstances such as size of the pond and the percentage filled when establishing the five year closure timeframe. A majority of the final closure obligation and compliance costs will be focused on historic material that is already in the ponds so a change in future generation will not negate the obligation to comply with the CCR regulation when it is issued. However, as a result of Vectren’s previous investments in dry fly ash handling and beneficial reuse activities, the volume of new material added to the ponds since 2009 has been significantly decreased. As a direct result of the TVA spill referenced above, the EPA undertook to inspect all surface impoundments and dams holding combustion by-products. The EPA conducted site assessments at Vectren's AB Brown and FB Culley facilities and found the facilities' surface impoundments to be satisfactory and not posing a high hazard. WATER There are multiple regulatory rulemakings that could, when finalized, require more stringent limits for power plant discharges. The EPA is developing new Effluent Limit Guidelines and Standards (ELGS) for the Steam Electric Power Generating Point Source Category. A draft was issued June 7, 2013, with a final rule scheduled for September 2015. The draft rule requested comment on 8 different options for treatment standards and compliance locations that ranged from no change of November 2014 Page 61

2014 Integrated Resource Plan

current standards to a requirement for full zero liquid discharge. Of the eight options, the EPA identified four “preferred” options. For the preferred options, the size of Vectren’s units would drop the plants out of the requirement for specific treatment and discharge limits for Flue Gas Desulfurization (FGD) waste water or bottom ash transport water in 2 of the 4 options. Instead, IDEM would apply Best Professional Judgment (BPJ) which takes into consideration site specific factors. While Vectren acknowledges that the EPA’s final ELGs could further alter discharge parameters and limits, it is not possible at this time to predict the outcome of the final rule. Vectren believes its chosen treatment systems are the most cost effective option for meeting its current permits while limiting potential stranded costs when new regulations take effect. The EPA released its final rule regulating cooling water structures under Section 316(b) of the Clean Water Act (CWA) on August 15, 2014. Section 316(b) requires that intake structures that withdraw > 2 MGD of water, including most electric generating units, use the "Best Technology Available" to prevent and / or mitigate adverse environmental impacts to shellfish, fish, and wildlife in a water body. The rule lists separate sampling and study programs to minimize entrainment (pulling small organisms into the intake structure) and impingement (trapping or pinning fish against the exterior of the intake structure).

In addition, three additional studies are required that look at technical

feasibility and treatment costs, cost benefits evaluation, and non-water quality environmental impacts of the potential treatment option. These studies, combined with the results of the in-river fish sampling will help determine potential treatment options. Seven options were identified as pre-approved methods for complying with impingement mortality standards. While cooling towers are listed as an option, they are not mandated for existing facilities. Vectren does not believe cooling tower retrofits will be required at FB Culley due to its size and location on the Ohio River. The EPA acknowledges that for many facilities, the process of conducting the studies, determining the best treatment option, constructing the selected option, and confirming the adequacy of the treatment may take a minimum of 8 years from the time the rule November 2014 Page 62

2014 Integrated Resource Plan

becomes effective. Vectren's FB Culley units currently use a "once through" cooling water intake system and are affected by this proposed regulation. Vectren's AB Brown units use a closed cooling water system. However, under the final rule Vectren would still be required to submit documentation and study reports to confirm the existing cooling water tower mitigates impingement and entrainment.

November 2014 Page 63

2014 Integrated Resource Plan

This page intentionally left blank for formatting purposes

November 2014 Page 64

2014 Integrated Resource Plan

CHAPTER 5 SALES & DEMAND FORECAST

November 2014 Page 65

2014 Integrated Resource Plan

INTRODUCTION The electric energy and demand forecasts provide the basis for evaluation of supplyside and demand-side options to meet the electric needs of Vectren’s customers. These forecasts reflect local and regional economic impacts, the effects of past, present, and proposed Demand Side Management / Demand Response (DSM/DR) programs, mandated efficiency standards, and the effects of normal market forces on electricity sales. Overview of Vectren’s Customers Vectren provides delivery services to approximately 142,000 electric residential, general service (commercial), and large (primarily industrial) customers with electricity in southwestern Indiana.

A high proportion of Vectren’s sales are made to electric-

intensive general service and large customers. In 2013, about 29% of Vectren’s annual retail electric energy sales were consumed by residential customers, 23% of sales were consumed by General Service (GS), and 48% of sales were consumed by more than 100 large customers. Less than 1% served other load (street lights). Significant general service and large load creates complexity in load forecasting. These customers have the ability to significantly impact Vectren’s demand for electricity, as economic factors affect their businesses’ success. ELECTRIC LOAD FORECAST OVERVIEW Vectren developed low, base, and high forecasts of annual energy sales and requirements (e.g. sales plus related delivery losses) and peak loads (e.g. demand plus losses) for the purposes of its IRP. These forecasts, and the activities undertaken to develop them, are described in this section. Development of the Vectren system-wide long-term electric load forecast involves the aggregation of multiple models.

Vectren uses statistically adjusted end use (SAE)

modeling and econometric modeling to forecast customer needs for the future. Vectren has investigated the use of pure end-use modeling for forecasting purposes but November 2014 Page 66

2014 Integrated Resource Plan

believes that a combination of statistically adjusted end-use and econometric modeling best accommodates its forecasting needs. End-use modeling involves building and maintaining a detailed end-use database to capture appliance and thermal shell characteristics, as well as end-use consumption information. The basic structure of an end-use model is households multiplied by appliance saturation and unit energy consumption. Each component of the end-use model is modeled separately. For these reasons, end-use modeling is very expensive to develop and maintain. It is meant primarily for long-term modeling (5-20 years). Often, a separate short term forecast is necessary, which is hard to integrate with the long-term forecast.

Vectren utilizes

statistically adjusted end-use models to forecast residential and general service loads. Large customer needs are forecasted with an econometric linear regression model, while street lighting load is forecasted with a simple trend model.

The detail of

Vectren’s forecasting methodology is discussed later in this chapter. FORECAST RESULTS The base case forecasts of annual energy requirements and peak loads for the 2014 2034 planning period are provided in Tables 5-1 and 5-2. Annual energy requirements are projected to have a -.2% compound annual growth rate over the twenty year planning period. Peak requirements are projected to have a compound annual growth rate of -.1% over the twenty year planning period.

November 2014 Page 67

2014 Integrated Resource Plan

Table 5-1 Base Case Energy and Demand Forecast Annual Energy (GWh)

Peak (MW)

2014 Proj.

1,145

5,782

2015

1,155

5,914

2016

1,156

5,936

2017

1,113

5,514

2018

1,109

5,503

2019

1,106

5,494

2020

1,106

5,497

2021

1,106

5,492

2022

1,107

5,494

2023

1,107

5,494

2024

1,107

5,496

2025

1,106

5,487

2026

1,106

5,487

2027

1,107

5,492

2028

1,109

5,507

2029

1,110

5,509

2030

1,111

5,517

2031

1,111

5,523

2032

1,113

5,540

2033

1,114

5,548

2034

1,115

5,560

-0.1%

-0.2%

Compound Annual Growth Rate, 2014-2034 Including Wholesale

1

1

Year

Includes wholesale contract sales for 2014

November 2014 Page 68

2014 Integrated Resource Plan

Table 5-2 Base Case Energy Forecast by Customer Class

Year

2013 Calendar

Residential (GWh)

General Service (GWh)

1,435

1,294

Large (GWh)

Other (GWh)

Net DSM (GWh)

DG (GWh)

Wholesale (GWh)

Losses (GWh)

Total Requirements (GWh)

61

267

5,822

21

2,744

1,444

1,300

2,739

20

(47)

(1)

61

265

5,782

1,444

1,327

2,926

20

(72)

(1)

271

5,914

2016

1,448

1,351

2,945

20

(98)

(2)

272

5,936

2017

1,451

1,354

2,563

19

(123)

(3)

253

5,514

2018

1,458

1,357

2,567

19

(148)

(3)

252

5,503

2019

1,469

1,363

2,569

19

(173)

(5)

252

5,494

2020

1,475

1,370

2,574

19

(186)

(7)

252

5,497

2021

1,480

1,373

2,577

19

(199)

(9)

252

5,492

2022

1,490

1,380

2,579

19

(211)

(12)

252

5,494

2023

1,500

1,386

2,579

18

(224)

(17)

252

5,494

2024

1,514

1,395

2,578

18

(237)

(23)

252

5,496

2025

1,523

1,398

2,579

18

(250)

(32)

251

5,487

2026

1,534

1,404

2,579

18

(263)

(37)

251

5,487

2027

1,547

1,413

2,581

18

(276)

(42)

252

5,492

2028

1,562

1,427

2,584

18

(289)

(48)

252

5,507

2029

1,572

1,436

2,588

18

(302)

(55)

252

5,509

2030

1,586

1,445

2,593

18

(316)

(62)

253

5,517

2031

1,599

1,455

2,598

18

(329)

(71)

253

5,523

2032

1,616

1,473

2,604

18

(343)

(81)

254

5,540

2033

1,628

1,486

2,611

18

(356)

(93)

254

5,548

2034

1,644

1,501

2,619

18

(370)

(106)

255

5,560

Compound Annual Growth Rate for (20142034)

0.6%

0.7%

-0.2%

-0.7%

2014 Proj. 2015

-0.2%

Low and high energy and demand forecasts were developed by modifying the assumptions around conservation, distributed generation adoption, economic drivers, population projections, and large customer additions. The difference between the two high growth cases is slow steady growth or a large step up.

In the high growth

(modeled) forecast, economic growth was increased from approximately 1% to 2%, and population growth was increased from about .3% to .5%. The high growth (large load) case is the same as the base case, with the addition of a large customer in 2018. The results are shown in Table 5-3 and 5-4.

November 2014 Page 69

2014 Integrated Resource Plan

Table 5-3 Base, Low, and High Case Energy Forecasts

Base

Low Growth

High Growth (modeled)

High Growth (large load)

Annual Requirements

Annual Requirements

Annual Requirements

Annual Requirements

Year

GWh

2014 Proj.

5,782

2015

5,914

2.3%

5,907

2.2%

5,947

2.6%

5,914

2.3%

2016

5,936

0.4%

5,922

0.3%

5,990

0.7%

5,936

0.4%

2017

5,514

-7.1%

5,320

-10.2%

5,609

-6.4%

5,514

-7.1%

2018

5,503

-0.2%

5,302

-0.3%

5,645

0.6%

6,098

10.6%

2019

5,494

-0.2%

5,287

-0.3%

5,681

0.6%

6,088

-0.2%

2020

5,497

0.1%

5,290

0.1%

5,712

0.5%

6,090

0.0%

2021

5,492

-0.1%

5,285

-0.1%

5,734

0.4%

6,085

-0.1%

2022

5,494

0.0%

5,286

0.0%

5,764

0.5%

6,087

0.0%

2023

5,494

0.0%

5,284

0.0%

5,799

0.6%

6,085

0.0%

2024

5,496

0.1%

5,285

0.0%

5,841

0.7%

6,088

0.0%

2025

5,487

-0.2%

5,273

-0.2%

5,870

0.5%

6,077

-0.2%

2026

5,487

0.0%

5,272

0.0%

5,909

0.7%

6,077

0.0%

2027

5,492

0.1%

5,276

0.1%

5,950

0.7%

6,081

0.1%

2028

5,507

0.3%

5,288

0.2%

5,997

0.8%

6,095

0.2%

2029

5,509

0.1%

5,289

0.0%

6,028

0.5%

6,097

0.0%

2030

5,517

0.1%

5,293

0.1%

6,060

0.5%

6,104

0.1%

2031

5,523

0.1%

5,296

0.0%

6,094

0.6%

6,109

0.1%

2032

5,540

0.3%

5,310

0.3%

6,132

0.6%

6,127

0.3%

2033

5,548

0.1%

5,312

0.0%

6,157

0.4%

6,133

0.1%

2034

5,560

0.2%

5,320

0.1%

6,188

0.5%

6,145

0.2%

Compound Annual Growth Rate for (20142034)

Growth,%

GWh

Growth,%

5,782

-0.2%

GWh

Growth,%

5,799

-0.4%

GWh

Growth,%

5,782

0.3%

0.3%

November 2014 Page 70

2014 Integrated Resource Plan

Table 5-4 Base, Low, and High Case Demand Forecasts

Base

Low Growth

High Growth (modeled)

High Growth (large load)

Annual Requirements

Annual Requirements

Annual Requirements

Annual Requirements

Year

MW

2014 Proj.

1,145

2015

1,155

0.8%

1,153

0.7%

1,160

1.0%

1,155

0.8%

2016

1,156

0.1%

1,153

-0.1%

1,164

0.3%

1,156

0.1%

2017

1,113

-3.7%

1,088

-5.6%

1,127

-3.2%

1,113

-3.7%

2018

1,109

-0.3%

1,083

-0.5%

1,130

0.3%

1,208

8.6%

2019

1,106

-0.3%

1,079

-0.4%

1,133

0.3%

1,205

-0.3%

2020

1,106

0.0%

1,079

0.0%

1,136

0.3%

1,206

0.0%

2021

1,106

0.0%

1,079

0.0%

1,139

0.3%

1,206

0.0%

2022

1,107

0.1%

1,080

0.0%

1,143

0.3%

1,206

0.0%

2023

1,107

0.0%

1,079

0.0%

1,147

0.4%

1,206

0.0%

2024

1,107

0.0%

1,079

0.0%

1,152

0.4%

1,206

0.0%

2025

1,106

-0.1%

1,077

-0.2%

1,155

0.3%

1,205

-0.1%

2026

1,106

0.0%

1,077

0.0%

1,160

0.4%

1,205

0.0%

2027

1,107

0.1%

1,078

0.1%

1,165

0.4%

1,206

0.1%

2028

1,109

0.2%

1,079

0.1%

1,171

0.5%

1,207

0.1%

2029

1,110

0.1%

1,079

0.0%

1,175

0.3%

1,208

0.0%

2030

1,111

0.1%

1,080

0.0%

1,179

0.3%

1,209

0.1%

2031

1,111

0.0%

1,080

0.0%

1,183

0.3%

1,209

0.0%

2032

1,113

0.2%

1,081

0.1%

1,187

0.4%

1,211

0.1%

2033

1,114

0.1%

1,081

0.0%

1,190

0.2%

1,211

0.1%

2034

1,115

0.1%

1,081

0.0%

1,193

0.3%

1,212

0.1%

Compound Annual Growth Rate for (20142034)

Growth,%

MW

Growth,%

1,145

-0.1%

MW

Growth,%

1,148

-0.3%

MW

Growth,%

1,145

0.2%

0.3%

November 2014 Page 71

2014 Integrated Resource Plan

FORECAST INPUTS & METHODOLOGY Forecast Inputs Energy Data Historical Vectren sales and revenues data were obtained through an internal database. The internal database contains detailed customer information including rate, service, North American Industrial Classification System (NAICS) codes (if applicable), usage, and billing records for all customer classes (more than 15 different rate and customer classes). These consumption records were exported out of the database and compiled in a spreadsheet on a monthly basis. The data was then organized by rate code and imported into the load forecasting software. Economic and Demographic Data Economic and demographic data was provided by Moody’s Economy.com for the nation, the state of Indiana, and the Evansville Metropolitan Statistical Area (MSA). Moody’s Economy.com, a division of Moody’s Analytics, is a trusted source for economic data that is commonly utilized by utilities for forecasting electric sales. The monthly data provided to Vectren contains both historical results and projected data throughout the IRP forecast period. This information is input into the load forecasting software and used to project residential, GS, and large sales. Weather Data The daily maximum and minimum temperatures for Evansville, IN were obtained from DTN, a provider of National Oceanic and Atmospheric Administration (NOAA) data. NOAA data is used to calculate monthly heating degree days (HDD) and cooling degree days (CDD). HDDs are defined as the number of degrees below the base temperature of 65 degrees Fahrenheit for a given day. CDDs are defined as the number of degrees above the base temperature of 65 degrees Fahrenheit for a given day. HDDs and CDDs are averaged on a monthly basis. Normal degree days, as obtained from NOAA,

November 2014 Page 72

2014 Integrated Resource Plan

are based on a thirty year period. Historical weather data1 is imported into the load forecasting software and is used to normalize the past usage of residential and GS customers. Similarly, the projected normal weather data is used to help forecast the future weather normalized loads of these customers. Equipment Efficiencies and Market Shares Data Itron Inc. provides regional Energy Information Administration (EIA) historic and projected data for equipment efficiencies and market shares. This information is used in the residential average use model and GS sales model. Note that in 2013 an appliance survey of Vectren’s residential customers was conducted to compare its territory market share data with the regional EIA data.

In order to increase the accuracy of the

residential average use model, regional equipment market shares were altered to reflect those of Vectren’s actual territory. Model Overview Changes in economic conditions, prices, weather conditions, as well as appliance saturation and efficiency trends drive energy deliveries and demand through a set of monthly customer class sales forecast models.

Monthly regression models are

estimated for each of the following primary revenue classes: 

Residential (residential average usage and customer models)

General Service

Large

Street Lighting

In the long-term, both economics and structural changes drive energy and demand growth. Structural changes are captured in the residential average use and general service sales forecast models through Statistically Adjusted End-Use (SAE) model specifications. The SAE model variables explicitly incorporate end-use saturation and 1

The large sales model also includes CDDs.

November 2014 Page 73

2014 Integrated Resource Plan

efficiency projections, as well as changes in population, economic conditions, price, and weather. End-use efficiency projections include the expected impact of new end-use standards and naturally occurring efficiency gains. The large sales forecast is derived using an econometric model that relates large sales mostly to regional manufacturing Gross Domestic Product (GDP) growth. Street light sales are forecasted using a simple trend and seasonal model. The results of the sales forecast modes are imported into the demand forecast model. The long-term demand forecast is developed using a “build-up” approach.

This

approach entails first estimating class and end-use energy requirements and then using class and end-use sales projections to drive system peak demand.

The forecast

models capture not only economic activity and population projections, but also expected weather conditions, the impact of improving end-use efficiency and standards, and electricity prices. The long-term system peak forecast is derived through a monthly peak linear regression model that relates monthly peak demand to heating, cooling, and base load requirements. The model variables incorporate changes in heating, cooling, and baseuse energy requirements derived from the class sales forecast models as well as peakday weather conditions. Note that the forecast is adjusted to reflect future Vectren sponsored DSM impacts, expected adoption of customer owned distributed generation, and expected large customer additions. Figure 5-1 shows the general approach.

November 2014 Page 74

2014 Integrated Resource Plan

Figure 5-1: Forecast Approach

Analytic Methodology Used in Forecast Residential Average Use Model Residential customer usage is a product of heating, cooling, and other load.

Both

heating and cooling are weather sensitive and must be weather normalized in a model to remove weather noise from projections. Other major drivers of load are historical and projected market saturation of electronics, appliances, and equipment and their respective efficiencies. Vectren’s service territory has a high saturation rate of central air conditioning equipment that is growing at a very slow pace, which helps to minimize average use growth.

As equipment wears out and is replaced with newer, more

efficient equipment, the average energy use per customer (AUPC) is reduced. Although there is increasing use of household electronics and appliances, this is balanced by increasing efficiencies in these areas. High tech devices like televisions, computers, and set-top boxes will see improving efficiencies, driven by innovation, competition, and voluntary agreements like the Energy Star program.

Changes in

lighting standards are having a large impact on energy consumption and will continue to impact residential customer usage in the years to come. November 2014 Page 75

2014 Integrated Resource Plan

Even before Vectren sponsored DSM program savings, use per customer is largely flat, increasing only by 0.2% annually through 2024. This is largely due to the continuing phase-out of the most common types of incandescent light bulbs mandated by the Energy Independence and Security Act (EISA) and new end-use efficiency standards recently put in place by the Department of Energy (DOE).

Average use begins to

increase at a slightly faster rate in the later years, as the Energy Information Administration (EIA) baseline intensity projections only include those end-use standards that are currently law.

Note that DOE continues to propose new energy efficiency

standards. The price of electricity and household income also influence average customer energy use. In general, there is a positive correlation between household income and usage. As household income rises, total usage rises. correlation between price and usage.

Conversely, there is a negative

As price goes up, average use goes down.

Finally, the size of the home (number of inhabitants and square footage) and the thermal integrity of the structure affect residential consumption. The residential average use model is a statistically adjusted end-use (SAE) model that addresses each of the previously discussed drivers of residential usage. SAE models incorporate many of the benefits of econometric models and traditional end-use models, while minimizing the disadvantages of each. SAE models are ideal for identifying sales trends for short-term and long-term forecasting. They capture a wide variety of relevant data, including economic trends, equipment saturations and efficiencies, weather, and housing characteristics. Additionally, SAE models are cost effective and are easy to maintain and update. In the SAE model, use is defined by three primary end uses: heating (XHeat), cooling (XCool), and other (XOther). XHeat, XCool, and XOther are explanatory variables in the model

November 2014 Page 76

2014 Integrated Resource Plan

that explain customer usage. By design, the SAE model calibrates results into actual sales.

The end-use variables incorporate both a variable that captures short-term utilization (Use) and a variable that captures changes in end-use efficiency and saturation trends (Index). The heating variable is calculated as:

Where

The cooling variable is defined as:

Where

XOther captures non-weather sensitive end-uses:

November 2014 Page 77

2014 Integrated Resource Plan

Where

Monthly residential usage was regressed on the XHeat, XCool, and XOther variables. The average use model is estimated over the period January 2003 through December 2013. The model explains historical average use well with an Adjusted R2 of 0.95 and in-sample MAPE of 3.3%. Residential Customers Model

Figure 5-2 Vectren Service Territory Map

A simple linear regression model was used

to

predict

the

number

of

residential customers. The number of residential customers was forecasted as a function of population projections for

the

Evansville

Metropolitan

Statistical Area (MSA) from Moody’s Economy.com.

There is a strong

correlation between the number of customers and population. The Evansville MSA is a good proxy for

the

Vectren

service

territory.

Figure 5-2 shows Vectren’s service territory (in red) and the Evansville MSA

in

gray.

The

number

of

residential customers is projected to grow an average of .27% per year throughout the planning period. The adjusted R2 for this model was .992, while the MAPE was .09%. November 2014 Page 78

2014 Integrated Resource Plan

General Service (GS) Sales Model Like the residential model, the general service (commercial) SAE sales model expresses monthly sales as a function of XHeat, XCool, and XOther. The end-use variables are constructed by interacting annual end-use intensity projections (EI) that capture end-use efficiency improvements, with non-manufacturing output (GDP) and employment (ComVarm), real price (Pricem), and monthly HDD and CDD:

The coefficients on price are imposed short-term price elasticities. A monthly forecast sales model is then estimated as:

Commercial Economic Driver Output and employment are combined through a weighted economic variable where ComVar is defined as:

Employment and nonmanufacturing output are weighted equally. The weights were determined by evaluating the in-sample and out-of-sample model statistics for different sets of employment and output weights. The resulting commercial sales model performs well with an Adjusted R2 of 0.95 and an in-sample MAPE of 2.2%.

November 2014 Page 79

2014 Integrated Resource Plan

Commercial sales growth averages 1.9% per year through 2016, as economic growth projections are relatively strong through this period. Real output is projected to increase at 2.2% with employment increasing 1.9%. After 2016, both output and employment growth slow with output averaging 0.5% growth and employment largely flat through 2024. Commercial sales, in turn, slow averaging 0.4% annually between 2016 and 2024. Large Sales Model The industrial sales forecast is based on a generalized monthly regression model where industrial sales are specified as a function of manufacturing employment, output, monthly CDD, and monthly binaries to capture seasonal load variation and shifts in the data. The economic driver is a weighted combination of real manufacturing output and manufacturing employment. The industrial economic (IndVar) variable is defined as:

The imposed weights are determined by evaluating in-sample and out-of-sample statistics for alternative weighting schemes. The final model’s Adjusted R2 is 0.65 with in-sample MAPE of 6.7%. The relatively low Adjusted R2 and relatively high MAPE are due to the “noisy” nature of industrial monthly billing data. There are many variables that impact large customer consumption that are not easily forecasted. These unforeseeable impacts make forecasting GS and large customers’ usage with a high degree of certainty very difficult, as these customers’ usage is extremely sensitive to economic conditions. Lighting Sales Model Street light sales are fitted with a simple seasonal exponential smoothing model with a trend term. Street lighting sales have been declining and are expected to continue to

November 2014 Page 80

2014 Integrated Resource Plan

decline through the forecast period as increasing lamp efficiency outpaces installation of new street lights. The model yielded an adjusted R2 of .769 and a MAPE of 5.34%. Vectren’s total energy requirements include forecasted sales for the four sectors described above, wholesale contracts, DSM savings, impact of customer owned distributed generation (DG) and delivery losses. Losses were estimated to be approximately 4.8 percent of requirements.

DSM savings and a forecast of

customer owned DG are highlighted separately in the sales forecast, and the DSM programs are discussed in detail in Chapter 8 DSM Resources. Peak Demand Forecast The Vectren energy forecast is derived directly from the sales forecast by applying a monthly energy adjustment factor to the monthly calendarized sales forecast.

The

energy adjustment factor includes line losses and any differences in timing between monthly sales estimates and delivered energy (unaccounted for energy).

Monthly

adjustment factors are calculated as the average monthly ratio of energy to sales. The long-term system peak forecast is derived through a monthly peak linear regression model that relates monthly peak demand to heating, cooling, and base load requirements:

The model variables (HeatVarm, CoolVarm, and BaseVarm) incorporate changes in heating, cooling, and base-use energy requirements derived from the class sales forecast models, as well as peak-day weather conditions. Heating and Cooling Model Variables Heating and cooling requirements are driven by customer growth, economic activity, changes in end-use saturation, and improving end-use efficiency. These factors are November 2014 Page 81

2014 Integrated Resource Plan

captured in the class sales forecast models. The composition of the models allows historical and forecasted heating and cooling load requirement to be estimated. The estimated model coefficients for the heating (XHeat) and cooling variables (XCool) combined with heating and cooling variable for normal weather conditions (NrmXHeat and NrmXCool) gives an estimate of the monthly heating and cooling load requirements. Heating requirements are calculated as:

B1 and C1 are the coefficients on XHeat in the residential and commercial models. Cooling requirements are estimated in a similar manner. As there is a small amount of cooling in the industrial sector, industrial cooling is included by multiplying the industrial model coefficient for the CDD variable by normal monthly CDD. Cooling requirements are calculated as:

B2 and C2 are the coefficients on XCool in the residential and commercial models and D2 is the coefficient on CDD in the industrial sales model. The impact of peak-day weather conditions is captured by interacting peak-day HDD and CDD with monthly heating and cooling load requirements indexed to a base year (2005). The peak model heating and cooling variables are calculated as:

November 2014 Page 82

2014 Integrated Resource Plan

Base Load Variable The peak model base load variable (BaseVarm) derived from the sales forecast models is an estimate of the non-weather sensitive load at the time of the monthly system peak demand. The base load variable is defined as:

Base load requirements are derived for each revenue class by subtracting out heating and cooling load requirements from total load requirements. Using the SAE modeling framework, class annual base load requirements are then allocated to end-uses at the time of monthly peak demand. For example, the residential water heating coincident peak load estimate is derived as:

Where ResWaterEI = Annual water heating intensity (water use per household) ResBaseEI = Annual base-use intensity (non-weather sensitive use per household) ResWaterFrac = Monthly fraction of usage on at peak (estimates are based on Itron’s hourly end-use load profile database) End-use load estimates are aggregated by end-use and then revenue class resulting in the base load variable. Model Results The model explains monthly peak variation well with an adjusted R2 of 0.97 and an insample MAPE of 2.5%.

November 2014 Page 83

2014 Integrated Resource Plan

CUSTOMER OWNED DISTRIBUTED GENERATION FORECAST Vectren has been monitoring national and regional distributed generation trends since the 2011 IRP. While a number of technologies continue to influence the electric utility industry, the primary focus is on distributed solar.

The present IRP considers the

potential for future customer-owned DG growth, specifically in the area of net metered distributed solar photovoltaic (PV) adoption. For modeling purposes, distributed PV is treated as a decrease in demand. A distributed solar forecast was developed using Vectren and Indiana historical net metering information and 3rd party data and assumptions. This forecast is presented below in Table 5-5.

November 2014 Page 84

2014 Integrated Resource Plan

Table 5-5 Distributed Solar Growth Forecast

Year Ending

1

Historic Peak Planning Capacity (MW)

Distributed Solar Adoption Forecasts: 1 Contribution to Peak Planning Capacity (MW)

LOW CASE

HIGH CASE

BASE CASE

2014

0.2

0.2

0.2

2015

0.3

0.3

0.3

2016

0.4

0.4

0.4

2017

0.5

0.6

0.6

2018

0.7

0.9

0.8

2019

0.9

1.2

1.1

2020

1.3

1.7

1.5

2021

1.7

2.4

2.0

2022

2.3

3.3

2.8

2023

3.0

4.7

3.9

2024

4.1

6.6

5.3

2025

5.5

9.2

7.3

2026

6.2

10.6

8.4

2027

7.0

12.1

9.6

2028

7.8

14.0

10.9

2029

8.9

16.1

12.5

2030

10.0

18.5

14.2

2031

11.3

21.2

16.3

2032

12.7

24.4

18.6

2033

14.3

28.1

21.2

2034

16.2

32.3

24.2

2006

0.002

2007

0.002

2008

0.003

2009

0.012

2010

0.029

2011

0.051

2012

0.106

2013

0.162

Peak planning capacity is 38% of installed capacity.

November 2014 Page 85

2014 Integrated Resource Plan

Because the IRP is concerned with meeting the annual peak demand, the data presented in Table 5-5 are expressed in terms of megawatts of peak planning capacity, rather than total direct current (DC) gross capacity or total alternating current (AC) inverter capacity. The summer peak typically occurs in late afternoon in mid-to-late summer, whereas maximum solar output is generally at noon in late spring or early summer. Because optimal solar output does not coincide with the summer peak, a factor must be applied to estimate the useful solar capacity from a given PV system at the summer peak. A wide range of peak planning capacity factors have been reported for distributed solar resources.1 Although MISO has not formally adopted a peak planning capacity factor, PJM, a regional transmission operator, has recommended a factor of 38%.2 Because of this PJM reference, Vectren has chosen to use this value. There may be further refinements on this going forward as the utility & solar industry further evaluate methodologies for developing this factor, and Vectren may revise this number in future IRPs. The historical data column reflects the summer peaking capacity of Vectren’s reported net metered customer accounts.3 The High, Low, and Base Case forecasts for the 2014 – 2034 planning horizon are derived from the following information & data sets: 

Vectren historical growth in net metered inverter-rated capacity,

Indiana historical growth in net metered inverter-rated capacity, and

Navigant Consulting solar capacity future growth rate assumptions for Indiana.4

High Case (applied to the low energy and demand forecast) calculation methodology is as follows: 

Vectren year-end 2013 inverter-rated capacity (426 kW) grows each year in a compounding manner using Navigant’s Indiana predicted growth rates as follows:

1

Sterling, John, and J. McLaren, M. Taylor, K. Cory. Treatment of Solar Resource Generation in Electric Utility Resource Planning. NREL/TP-6A20-60047. October, 2013. 2 PJM Manual 21: Rules and Procedures for Determination of Generating Capability, revision 11. PJM System Planning Department. March 5, 2014. 3 Vectren’s Customer-Generator Interconnection and Net Metering Report for year ended 12/13/2013. 4 Navigant Consulting, 5/2/2014.

November 2014 Page 86

2014 Integrated Resource Plan

o 2014 – 2025: 40% per year o 2025 – 2034: 15% per year 

Each year’s result is then multiplied by the factor 0.38 to arrive at the peak planning contribution for distributed solar.

Low Case (applied to the high (modeled) energy and demand forecast) calculation methodology is as follows: 

Vectren year-end 2013 inverter-rated capacity (426 kW) grows each year in a compounding manner using slower growth rates as follows: o 2014 – 2025: 34.1% per year o 2025 – 2034: 12.8% per year o These growth rates are a modified version of the High Case’s Navigant Indiana rates based on a derived factor. 

This growth “adjustment” factor is derived by taking historical net metered capacity growth in Vectren territory versus Indiana as a whole.

Specifically, this adjustment factor takes the simple average growth rate for Vectren for the years 2010 through 2012 and divides this result by the simple average growth rate for Indiana over the same period.

This adjustment factor is 0.852 (or 85.2%). Applying this factor to Navigant’s Indiana growth rates yields the 34.1% and 12.8% values given above.

Each year’s result is then multiplied by the factor 0.38 to arrive at the peak planning contribution for distributed solar.

Base Case (applied the base case and high (large load) energy and demand forecasts) calculation methodology is as follows: 

Takes the simple average of the High and Low cases in each year.

November 2014 Page 87

2014 Integrated Resource Plan

Each year’s result is then multiplied by the factor 0.38 to arrive at the peak planning contribution for distributed solar.

The overall approach for the High, Low, and Base cases is a reflection of the difference in the overall net-metered distributed generation customer adoption rates between Vectren and Indiana. It takes a very high level view of how solar adoption may evolve over a relatively long planning horizon. Vectren believes that the long term nature of the IRP process calls for a high level macro approach, and the Navigant assumptions, while very general in nature, represent the results of expert analysis and therefore are an appropriate basis for making this forecast. Navigant did suggest an “adjustment factor” for the Vectren territory because the Vectren service territory is growing at a slower rate than the state of Indiana, resulting in the use of this in the Low case (and indirect use in the Base Case). The High Case utilizes the unadjusted, original Navigant growth rates (where the Vectren growth rate matches the overall state growth rate). While distributed solar PV, is the most prominent form of distributed generation anticipated in terms of total numbers of customers, it is not the only DG technology to be considered.

Cogeneration, or Combined Heat and Power (CHP), is also a key

technology category in the context of the IRP. However, because of the case-by-case nature of these potential resources, and the fact that some could be large enough to be modeled as a generation and/or capacity resource, these are covered outside this section on distributed generation. Additional future technologies in the distributed generation space include: 

Small wind turbines

Energy storage

Fuel cells

Micro turbines

Other Micro-CHP (e.g. small advanced engine technologies)

November 2014 Page 88

2014 Integrated Resource Plan

Micro grids (i.e. customer-sited distribution systems that may include generation and storage technologies)

Each of these technologies will be an important area for the industry to consider in coming years. At this time, none of these are significant enough (or certain enough) to be forecasted as customer-sited DG resources in the present IRP. However, Vectren will continue to monitor and consider how these technologies play into generation planning going forward. OVERVIEW OF LOAD RESEARCH ACTIVITIES Vectren has interval meters installed on a sample of residential and GS customers. Large customers who have a monthly minimum demand obligation of 300kVA are required to have interval meters installed. Vectren collects and stores this information for analysis as needed. Detailed load shapes are used to better understand customers’ usage, primarily for cost of service studies.

For this IRP, class load shapes were

borrowed from Itron’s Indiana library to break down Vectren’s hourly load profile by class. The load shapes were applied to historical peak demand. Graph 5-1 shows daily class contribution to peak for 2013.

November 2014 Page 89

2014 Integrated Resource Plan

Graph 5-1 Daily Class Contribution to Peak for 2013 (MW)

The following graphs (5-2 through 5-4) show the actual system load by day for 2013, the actual summer peak day for 2013 by hour, and the winter peak day for 2013 by hour. Note that these graphs do not include wholesale contract sales. Also additional load shapes are included in the Technical Appendix, section C.

November 2014 Page 90

2014 Integrated Resource Plan

Graph 5-2 Total System Load for 2013 (MW)

Graph 5-3 Summer Peak 2013 (MW)

November 2014 Page 91

2014 Integrated Resource Plan

Graph 5-4 Winter Peak 2013 (MW)

APPLIANCE SATURATION SURVEY AND CONTINUOUS IMPROVEMENT Vectren typically surveys residential customers every other year.

A residential

appliance saturation survey was conducted in the summer of 2013. The survey was completed by a representative sample of customers. Results from this survey were used to reflect market shares of actual residential customers. The residential average use model statistics were improved by calibrating East South Central Census regional statistics with the appliance saturation of Vectren’s customers. Note that Vectren’s service area is technically in the southern most point of the East North Central Census region, bordering the Ease South Central region.

Model results were improved by

calibrating to the East South Central region. At this time, Vectren does not conduct routine appliance saturation studies of GS and large customers. These customers are surveyed when needed for special programs. However, Vectren’s large and GS marketing representatives maintain close contact with its largest customers.

This allows Vectren to stay abreast of pending changes in

demand and consumption of this customer group.

November 2014 Page 92

2014 Integrated Resource Plan

Vectren continually works to improve our load forecasting process in a variety of ways. First, Vectren is a member of Itron’s Energy Forecasting Group.

The Energy

Forecasting Group contains a vast network of forecasters from around the country that share ideas and study results on various forecasting topics. Vectren forecasters attend an annual meeting that includes relevant topic discussions along with keynote speakers from the EIA and other energy forecasting professionals. The meeting is an excellent source for end-use forecasting directions and initiatives, as well as a networking opportunity. Vectren forecasters periodically attend continuing education workshops and webinars on various forecasting topics to help improve skills and learn new techniques. Additionally, Vectren discusses forecasts with the State Utility Forecasting Group and other Indiana utilities to better understand their forecasts. We compare and contrast our model assumptions and results to these groups to gain a better understanding of how they interpret and use model inputs. OVERVIEW OF PAST FORECASTS The following tables outline the performance of Vectren’s energy and demand forecasts. Forecasts from previous IRP filings from 2004 through 2013 were compared to actual values in order to evaluate the reliability of Vectren’s past energy and demand forecasts. The following tables show the actual and forecasted values for: 

Total Peak Demand

Total Energy

Residential Energy

GS Energy

Large Energy

Tables 5-6 through 5-10 present comparisons of actual values versus forecasted values from previous IRP filings. The percentage deviation of the actual values from the most recent forecast is shown in the last column of each table. The deviations of the total energy and total peak forecasts are better than for the individual classes, which is to be expected. Note that all of the forecasted values are weather-normalized, but the actual November 2014 Page 93

2014 Integrated Resource Plan

loads are not. This comparison would show much closer correlation if the actual loads were normalized to match the forecasts. This is particularly true when predicting the peak hour of the year. For example, weather in 2012 was abnormally hot, with multiple 100 degree days in a row, causing the peak demand to be high. 2013 was much milder and, therefore had a lower peak demand. Another factor affecting forecasts is the economic forecast. The recovery from the Great Recession has been much slower than expected.

Another source of potential error is the use of the direct load control

program, which reduces the peak demand on hot days by cycling off customer appliances to reduce system load.

Note that Vectren is not forecasting any firm

wholesale contracts after 2014.

Table 5-6 Total Peak Requirements (MW) Forecasts

Year 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013

Actual 1,222 1,316 1,325 1,341 1,166 1,143 1,275 1,221 1,205 1,102

Compound Annual Growth Rate, 2004-2013

-1.15%

2011

2009

2007

2005

2004 1,313

1,326 1,346 1,184 1,216 1,153 1,179 1,168 1,168

2001 1,325

Deviation from most recent forecast, % -8.4% 0.2% -0.1% -0.4% -1.6% -6.4% 9.6% 3.4% -3.1% 6.0%

November 2014 Page 94

2014 Integrated Resource Plan

Table 5-7 Total Energy Requirements (GWh)

2001

Deviation from prior IRP forecast, %

6,437

-2.1%

Forecasts Year

Actual

2004

6,303

2011

2009

2007

2005

2004

2005

6,508

2006

6,352

6,543

-3.0%

2007

6,527

6,210

4.9%

2008

5,931

6,160*

-3.9%

2009

5,598

6,068

-8.4%

2010

6,221

5,608

9.9%

2011

6,244

5,762

7.7%

2012

5,861

5,896

0.6%

2013 Compound Annual Growth Rate, 2004-2013

5,822

5,867

0.8%

6,624

-1.8%

-0.88%

*Adjusted to include wholesale sales

Table 5-8 Residential Energy Sales (GWh)

2001

Deviation from prior IRP forecast, %

1,553

-3.4%

Forecasts Year

Actual

2004

1,502

2005

1,571

2006

1,475

2011

2009

2007

2005

2004 1,546

1,584 1,609

1.6% -7.4%

2007

1,631

2008

1,435

1.3%

2009

1,449

2010

1,598

1,467

2011

1,515

1,451

2012

1,456

1,501

-3.1%

2013

1,427

1,483

-3.9%

Compound Annual Growth Rate, 2004-2013

0.57%

1,581

-10.1%

1,595

-10.0% 8.2% 4.2%

November 2014 Page 95

2014 Integrated Resource Plan

Table 5-9 General Service Energy Sales (GWh) Forecasts (GS) 2011

2009

2007

2005

2004

2001

Deviation from prior IRP forecast, %

Year

Actual

2004

1,502

2005

1,556

2006

1,515

1,566

-3.4%

2007

1,412

1,594

-12.9%

2008

1,294

1,380

-6.6%

2009

1,299

1,384

-6.5%

2010

1,361

1,275

2011

1,335

1,285

2012

1,315

1,387

-5.5%

2013

1,303

1,409

-8.2%

Compound Annual Growth Rate, 2004-2013

1.57%

1,408 1,500

6.3% 3.6%

6.3% 3.8%

Table 5-10 Large Energy Sales (GWh)

2001

Deviation from prior IRP forecast, %

2,570

-9.5%

Forecasts (Large) Year

Actual

2004

2,346

2011

2009

2007

2005

2004

2005

2,389

2006

2,376

2007

2,538

2008

2,744

2009

2,251

2010

2,601

2,281

12.3%

2011

2,744

2,445

10.9%

2012

2,714

2,696

0.7%

2013

2,744

2,714

1.1%

Compound Annual Growth Rate, 2004-2013

1.76%

2,619 2,379 2,422

-9.6% -0.1% 4.6%

2,591

5.6%

2,598

-15.4%

November 2014 Page 96

2014 Integrated Resource Plan

This page intentionally left blank for formatting purposes

November 2014 Page 97

2014 Integrated Resource Plan

CHAPTER 6 ELECTRIC SUPPLY ANALYSIS

November 2014 Page 98

2014 Integrated Resource Plan

INTRODUCTION The purpose of the electric supply analysis is to determine the best available technologies for meeting the potential future supply-side resource needs of Vectren. A very broad range of supply alternatives were identified in a Technology Assessment described below. These supply alternatives were screened, and a smaller subset of alternatives were chosen for the final planning and integration analysis. Demand side alternatives play a major role in the integrated plan and are discussed in Chapter 8 DSM Resources. The supply-side alternatives which are discussed here fall into two basic categories: 

construction of new generating facilities and

energy and capacity purchases.

Note that additional DSM energy efficiency programs beyond what was included in the base case energy and demand forecasts were modeled competed with supply-side options to meet future load requirements. This is discussed further in Chapter 8 DSM Resources. TECHNOLOGY ASSESSMENT For the 2014 Electric IRP process, Vectren retained the services of Burns & McDonnell, one of the leading engineering design experts in the United States, to assist in performing a Technology Assessment for generation technologies. The Technology Assessment can be found in the Technical Appendix, section B. Below are descriptions of the technologies that were considered from the Technology Assessment. Natural Gas Technologies The simple cycle gas turbines (SCGT) utilize natural gas to produce power in a gas turbine generator. The gas turbine cycle is one of the most efficient cycles for the conversion of gaseous fuels to mechanical power or electricity. Typically, SCGTs are used for peaking power due to their fast load ramp rates and relatively low capital costs. November 2014 Page 99

2014 Integrated Resource Plan

However, the units have high heat rates compared to other technologies. The different classes of SCGTs are shown below in Table 6-1. Please note that for new natural gas fired units, the capital costs shown in the table above are higher than the overnight costs shown in the Technology Assessment document. A 30% contingency for gas infrastructure siting costs and owner’s costs was added for final modeling purposes. Table 6-1 SGCT Classes SimpleCycleGasTurbine BaseLoadNetOutput(MW) BaseLoadNetHeatRate(HHVBtu/kWh) BaseProjectCosts(2014$/kW) FixedO&MCosts(2014$/kW‐yr.)

LM6000

LMS100

E‐Class

F‐Class

49.1

106.4

87.5

212.8

9,570

8,860

11,480

9,940

$2,047

$1,440

$1,704

$1,228

$23.98

$11.18

$16.56

$7.42

The combined cycle gas turbines (CCGT) utilize natural gas to produce power in a gas turbine which can be converted to electric power by a coupled generator, and to also use the hot exhaust gases from the gas turbine to produce steam in a heat recovery steam generator (HRSG).

This steam is then used to drive a steam turbine and

generator to produce electric power. The use of both gas and steam turbine cycles in a single plant to produce electricity results in high conversion efficiencies and low emissions. For this assessment, a 1x1, 2x1, and 3x1 power block, as shown in Table 62, was evaluated with General Electric (GE) 7F-5 turbines as representative CCGT technology. A 1x1 means one gas or steam turbine is coupled with one HRSG. A 2x1 means two gas or steam turbines are coupled with one HRSG. A 3x1 follows the same pattern, meaning that there are three gas or steam turbines coupled with one HRSG.

November 2014 Page 100

2014 Integrated Resource Plan

Table 6-2 CCGT Classes CombinedCycleGasTurbine

1x1F‐Class Unfired

2x1F‐Class Unfired

3x1F‐Class Unfired

405.5

815.5

1227.1

6,610

6,530

6,500

$1,400

$1,083

$925

$13.51

$7.62

$5.79

BaseLoadNetOutput(MW) BaseLoadNetHeatRate(HHV Btu/kWh) BaseProjectCosts(2014$/kW) FixedO&MCosts(2014$/kW‐yr)

The reciprocating engine is the last of the natural gas alternative technologies evaluated. The reciprocating, or piston, engine operates on the conversion of pressure into rotational energy that will fire on natural gas. Fuel and air are injected into a combustion chamber prior to its compression by the piston assembly of the engine. A spark ignites the compressed fuel and air mixture causing a rapid pressure increase that drives the piston downward. The piston is connected to an offset crankshaft, thereby converting the linear motion of the piston into rotational motion that is used to turn a generator for power production. The reciprocating engine is shown in Table 6-3. Table 6-3 Reciprocating Engine ReciprocatingEngine BaseLoadNetOutput(MW) BaseLoadNetHeatRate(HHV Btu/kWh) BaseProjectCosts(2014$/kW) FixedO&MCosts(2014$/kW‐yr)

100.2 8,470 $1,677 $11.79

November 2014 Page 101

2014 Integrated Resource Plan

Coal Technologies Pulverized coal steam generators are characterized by the fine processing of the coal for combustion in a suspended fireball. Coal is supplied to the boiler from bunkers that direct coal into pulverizers, which crush and grind the coal into fine particles. The primary air system transfers the pulverized coal from the pulverizers to the steam generator’s low NOx burners for combustion. The steam generator produces highpressure steam for throttle steam to the steam turbine generator. The steam expansion provides the energy required by the steam turbine generator to produce electricity. Another type of coal technology that was evaluated was the Integrated Gasification Combined Cycle (IGCC) technology. IGCC technology produces a low calorific value syngas from coal or solid waste that can be fired in a combined cycle power plant. The gasification process itself is a proven technology used extensively for chemical production of products such as ammonia for fertilizer. See Table 6-4 for further details on the coal technologies evaluated. Table 6-4 Coal Technologies Coal

BaseLoadNetOutput(MW) BaseLoadNetHeatRate(HHV Btu/kWh) BaseProjectCosts(2014$/kW) FixedO&MCosts(2014$/kW‐yr)

Supercritical Pulverized Coal1

Supercritical Pulverized Coal2

2x1 Integrated Gasification CC

425

637.5

482

10,500

10,200

11,470

$5,568

$5,080

$10,698

$32.41

$21.54

$36.88

November 2014 Page 102

2014 Integrated Resource Plan

Waste to Energy Technologies Stoker boiler technology is the most commonly used waste to energy (WTE) or biomass technology. Waste fuel is combusted directly in the same way fossil fuels are consumed in other combustion technologies. The heat resulting from the burning of waste fuel converts water to steam, which then drives a steam turbine generator for the production of electricity. The two fuel types evaluated in the IRP was wood and landfill gas which are represented in Table 6-5. Table 6-5 Waste to Energy Technologies Biomass BaseLoadNetOutput(MW) BaseLoadNetHeatRate(HHV Btu/kWh) BaseProjectCosts(2014$/kW) FixedO&MCosts(2014$/kW‐yr)

WoodStoker Fired

LandfillGas ICEngine

50

5

13,500

10,500

$4,542

$3,261

$94.49

$182.88

Renewable Technologies Four renewable technologies were evaluated in the IRP. Those technologies were wind energy, solar photovoltaic, solar thermal, and hydroelectric. Most of the data evaluated was taken from the Technology Assessment, but some data used was from updated studies or real-life examples which will be further discussed below. Wind turbines convert the kinetic energy of wind into mechanical energy, and are typically used to pump water or generate electrical energy that is supplied to the grid. Subsystems for either configuration typically include a blade or rotor to convert the energy in the wind to rotational shaft energy, a drive train, usually including a gearbox and a generator, a tower that supports the rotor and drive train, and other equipment,

November 2014 Page 103

2014 Integrated Resource Plan

including controls, electrical cables, ground support equipment and interconnection equipment. All the data evaluated for wind energy came from the Technology Assessment. The conversion of solar radiation to useful energy in the form of electricity is a mature concept with extensive commercial experience that is continually developing into diverse mix of technological designs. Solar conversion technology is generally grouped into Solar Photovoltaic (PV) technology, which directly converts sunlight to electricity due to the electrical properties of the materials comprising the cell, and Solar Thermal technology, which converts the radiant heat of the solar energy to electricity through an intermediary fluid. Photovoltaic (PV) cells consist of a base material (most commonly silicon), which is manufactured into thin slices and then layered with positively and negatively charged materials. At the junction of these oppositely charged materials, a "depletion" layer forms. When sunlight strikes the cell, the separation of charged particles generates an electric field that forces current to flow from the negative material to the positive material. This flow of current is captured via wiring connected to an electrode array on one side of the cell and an aluminum back-plate on the other. Solar Thermal technology transfers solar energy to an intermediary liquid (typically mineral oil or molten sodium and potassium nitrate salts) in the form of heat, which is then used to boil water and produce steam. That steam is sent to a Steam Turbine Generator (STG) for the production of electricity. The life expectancy of a solar thermal power plant is similar to that of any fossil fueled thermal plant as long as preventative and routing maintenance programs are undertaken. Vectren recognized that utility scale solar costs are expected to decline over the next few years and decided to have Burns & McDonnell revisit the solar portion of this Technology Assessment, which had a static cost for solar. Burns & McDonnell’s November 2014 Page 104

2014 Integrated Resource Plan

Phoenix office, which has extensive knowledge of the solar industry, developed an asymptotic curve, beginning at $1,880 per KWac in 2014, and declining to $1,500 per KWac in 2020 and staying flat in real terms for the remainder of the planning horizon. The declining cost curve was used for Vectren’s IRP modeling. The costs are represented in Table 6-6. Low-head hydroelectric power generation facilities are designed to produce electricity by utilizing water resources with low pressure differences, typically less than 5 feet head but up to 130 feet. Specially designed low-head hydro turbines are often current driven, and therefore operate at low speeds of 100 to 500 rpm in various configurations and orientations. Since they do not require a large head loss, low-head hydroelectric facilities can be incorporated in a variety of different applications, including rivers, canals, aqueducts, pipelines, and irrigation ditches. This allows the technology to be implemented much more easily than conventional hydropower, with a much smaller impact to wildlife and environmental surroundings. However, power supply is dependent on water supply flow and quality, which are sensitive to adverse environmental conditions such as dense vegetation or algae growth, sediment levels, and drought. Additionally, low-head hydropower is relatively new and undeveloped, resulting in a high capital cost for the relatively small generation output. Vectren utilized a previously performed study that included dams in and around Vectren’s electric service territory to help provide guidance for this IRP. The study was titled Hydropower Resource Assessment at Non-Powered USACE Sites and was prepared by the Hydropower Analysis Center for U. S. Army Corps of Engineers. The study was finalized in July 2013.1 Since there were no costs in the study, Vectren used a real-life example from a hydroelectric construction project in the area to gather the project costs. This data is represented in table 6-6.

1

Vectren referenced page 28 of this analysis.

November 2014 Page 105

2014 Integrated Resource Plan

Table 6-6 Renewable Technologies Renewable Wind

SolarPV

Solar Thermal

Hydroelectric

50

50

50

50

Intermittent (27%)

Intermittent (19%)

Intermittent (19%)

44%

$2,296

$1,8801

$5,740

$4,966

$25.40

$17.27

$35.56

$76.20

BaseLoadNetOutput(MW) CapacityFactor(energyannual output) BaseProjectCosts(2014$/kW) FixedO&MCosts(2014$/kW‐yr)

Energy Storage Technologies Two energy storage technologies were evaluated in the IRP. The technologies were batteries and Compressed Air Energy Storage (CAES). These are shown in Table 6-7. Electrochemical energy storage systems utilize chemical reactions within a battery cell to facilitate electron flow, converting electrical energy to chemical energy when charging and generating an electric current when discharged. Electrochemical technology is continually developing as one of the leading energy storage and load following technologies due to its modularity, ease of installation and operation, and relative design maturity. CAES offers a way of storing off-peak generation that can be dispatched during peak demand hours. To utilize CAES, the project needs a suitable storage site, either above ground or below ground, and availability of transmission and fuel source. CAES facilities use off-peak electricity to power a compressor train that compresses air into an underground reservoir at approximately 850 psig. Energy is then recaptured by releasing the compressed air, heating it (typically) with natural gas firing, and generating power as the heated air travels through an expander. 1

$1,880 per KWac in 2014, and declining to $1,500 per KWac in 2020 and staying flat in real terms for the remainder of the planning horizon.

November 2014 Page 106

2014 Integrated Resource Plan

Table 6-7 Energy Storage Technologies EnergyStorage

Compressed Advanced BatteryEnergy AirEnergy Storage Storage

BaseLoadNetOutput(MW) BaseProjectCosts(2014$/kW) FixedO&MCosts(2014$/kW‐yr)

10

135

$4,135

$1,240

$60.96

$7.11

Nuclear Technologies Manufacturers have begun designing Small Modular Reactors (SMRs) to create a smaller scale, completely modular nuclear reactor. These modular reactors are on the order of 30 feet in diameter and 300 feet high. The conceptual technologies are similar to Advanced Pressurized Water Reactors (APWR), and the entire process and steam generation is contained in one modular vessel. The steam generated in this vessel is then tied to a steam turbine for electric generation. The benefit of these SMRs is twofold; the smaller unit size will allow more resource generation flexibility and the modular design will reduce overall project costs while providing increased benefits in the areas of safety and concern, waste management, and the utilization of resources. The 225 MW SMR facility is shown in Table 6-8.

November 2014 Page 107

2014 Integrated Resource Plan

Table 6-8 Nuclear SMR Technology Nuclear BaseLoadNetOutput(MW) BaseLoadNetHeatRate(HHV Btu/kWh) BaseProjectCosts(2014$/kW) FixedO&MCosts(2014$/kW‐yr)

SmallModular Reactor 225 10,300 $5,415 $90.42

NEW CONSTRUCTION ALTERNATIVE SCREENING The first step in the analysis of new construction alternatives was to survey the available list of technologies and to perform a preliminary screening of each of the options, eliminating those options that were determined to be unfeasible or marginal. The power supply alternatives Vectren considered include intermediate and peaking options, as well as renewable generation, energy storage, distributed generation, and demand side management. These power supply alternatives were screened using a bus bar cost analysis. This was done in order to reduce the number of alternatives that were evaluated to a manageable level within Strategist, the planning model. The screening analysis was performed by developing and comparing levelized cost of each resource over a 20 year period. This simple approach is used to identify and limit the number of higher-cost generation alternatives. For screening purposes, estimated costs included fuel, operation & maintenance, and capital costs. Resources were then compared across various capacity factors in order to compare resource costs across all dispatch levels. Intermittent resources were compared at their respective output levels. Demand side management (DSM) and distributed generation (DG) were not considered in the bus bar analysis, but were considered alternatives within the IRP. See Chapter 5 Sales and Demand Forecast and Chapter 8 DSM Resources for more details.

November 2014 Page 108

2014 Integrated Resource Plan

The set of new construction alternatives that was selected for further assessment as a result of the screening process are presented in Table 6-9. The capital cost and O&M characteristics of these selected alternatives were assessed and developed in detail. Table 6-9 New Construction Alternatives Resource

1

7FA CCGT 1x1

Net Operating Capacity (MW) 405.5

Fuel Type

Accepted or Rejected as Resource Alternative

Reason to Accept or Reject

Natural Gas

Accept

Cost Effective Option Exceeds capacity needs. If pursuit of a Combined Cycle was needed, would consider coordinating with another utility in order to reduce costs. Exceeds capacity needs. If pursuit of a Combined Cycle was needed, would consider coordinating with another utility in order to reduce costs.

7FA CCGT 2x1

815.5

Natural Gas

Reject

7FA CCGT 3x1

1227.1

Natural Gas

Reject

1xLM6000

49.1

Natural Gas

Accept

Cost Effective for 50 MW or less

1xLMS100

106.4

Natural Gas

Reject

Not Cost Effective compared to alternatives

1xE-Class SCGT

87.5

Natural Gas

Reject

Not Cost Effective compared to alternatives

1xF-Class SCGT

212.8

Natural Gas

Accept

Cost Effective for low capacity factors

100 MW Recips

100.2

Natural Gas

Accept

Cost Effective for 100 MW or less

425

Coal

Reject

Not Cost Effective compared to alternatives

637.5

Coal

Reject

Not Cost Effective compared to alternatives

482

Coal

Reject

Not Cost Effective compared to alternatives

Wood Stoker Fired

50

Biomass

Reject

Not Cost Effective compared to alternatives

Landfill Gas IC Engine

5

Biomass

Reject

Not Cost Effective compared to alternatives

Reject

Not Cost Effective compared to alternatives

Reject

Not Cost Effective compared to alternatives

500 MW Supercritical Pulverized Coal 750 MW Supercritical Pulverized Coal 2x1 Integrated Gasification Combined Cycle

10 MW Adv. Battery Energy Storage 135 MW Compressed Air Energy Storage 50 MW Wind Energy Conversion

135 50

Renewables

Accept

Cost Effective Renewable Source

50 MW Solar PV

50

Renewables

Accept

Cost Effective Renewable Source

50 MW Solar Thermal

50

Renewables

Reject

Not Cost Effective compared to PV

50 MW Low-head Hydro

50

Renewables

Reject

Not Cost Effective compared to alternatives

Small Modular Nuclear

225

Uranium

Reject

Not Cost Effective compared to alternatives

1

10

Energy Storage Energy Storage

Resource options could be structured as a PPA or be utility owned

November 2014 Page 109

2014 Integrated Resource Plan

Gas-Fueled Technologies Two major types of gas-fired power generation technology, representing six alternatives, were selected for the detailed assessment. These were either simple cycle or combined cycle technology. 

Simple cycle gas turbine (SCGT) technology was evaluated for four levels of generating capability.

Combined cycle gas turbine (CCGT) technology was evaluated for two levels of generating capabilities.

Simple cycle alternatives were included in the final integration analysis. With respect to the combined cycle alternatives, this assumption was made on the basis of capturing economies of scale and high efficiencies while satisfying the reserve margin and capital investment constraints. Renewable Technologies Two renewable resources were included in the final integration analysis.

The

renewable resources were modeled in 50 MW blocks to be evaluated against the other new construction alternative options.

The 50 MW blocks are an installed capacity

(ICAP) or generation nameplate designation. The renewable technologies that were selected by the bus bar cost analysis included wind and solar photovoltaic (PV). These renewable resources are intermittent resources, meaning that they are not continuously available due to some factor outside direct control. Given that this analysis is based on unforced capacity (UCAP), the resources are converted from the installed capacity to the unforced capacity based on the percentage of the designated resource. For wind, 9.125% was used to calculate the amount of UCAP available. This effectively makes every 50 MW block of wind worth 4.56 MW towards meeting the UCAP requirement. For solar PV, 38% was used to calculate the amount of UCAP available. This makes every 50 MW block of solar PV worth 19 MW towards meeting the UCAP requirement. See Chapter 5 Sales and Demand Forecast for more details.

November 2014 Page 110

2014 Integrated Resource Plan

PURCHASED POWER ALTERNATIVES Another set of options available for assisting in meeting future supply-side resource requirements is purchased power from the wholesale electric market for both capacity and/or energy needs. Vectren is a participant in the wholesale electric power market and is a member of the ReliabilityFirst (RF), a regional reliability organization operating within the framework of the North American Electric Reliability Council (NERC). Vectren is also a member of MISO, the independent transmission system operator that serves much of the Midwest and Canada.

Estimating the future market price for electric energy available for purchase is difficult. In general, forward market information for "standard" products is available from brokers, counterparties, and published price indices.

However, the liquidity and price

transparency of the forward market is inversely proportional to the proximity of the delivery date of the product. The forward market becomes much less liquid (less trade volume) as the delivery date of the product moves further out into the future. Price discovery is more difficult as the more forward products are traded less and therefore less transparent. Capacity prices within MISO are on an upward trend that may last for several years. Vectren does not foresee a near term need for capacity. In the long run, regional reserve margins will approach equilibrium due to a combination of load growth and generation retirements. Capacity prices may converge with replacement build prices as surplus legacy capacity diminishes through unit retirements and market growth. If at some future point in time Vectren foresees a projected need for capacity, purchased power options will be fully and explicitly considered at that time.

November 2014 Page 111

2014 Integrated Resource Plan

CUSTOMER SELF- GENERATION Customer self-generation or behind the meter generation is likely to increase in the future. As discussed in in Chapter 5 Sales and Demand Forecast, a future trend of distributed rooftop solar has been projected and included in all scenarios. Somewhat more difficult to predict is the industrial adoption of behind the meter generation. One such facility is planned by a large industrial customer with a proposed implementation in 2017. As these types of projects become known they are incorporated into Vectren’s forecasts. They are not however a typical trend, and therefore, are not projected beyond the known projects.

Some large electric customers may be candidates for cogeneration opportunities. Vectren’s marketing department is in periodic discussions with customers most likely to participate in such a project. Should such a scenario develop, Vectren would work with that customer to see if they would benefit Vectren’s customers to participate in such a project by possibly increasing the output of the cogeneration plant and thus supplying the Vectren system with the excess. Such a project can only be evaluated on a case by case basis. RENEWABLE TECHNOLOGIES Wind As will be discussed further in Chapter 7 Renewables and Clean Energy, Vectren has two separate long-term purchase power agreements for a total of 80 MW of wind name plate capacity. These agreements were included in all integration analysis cases for the entire 20 year study period.

November 2014 Page 112

2014 Integrated Resource Plan

Other Landfill gas projects and biomass are viable renewable sources of energy. However, due to their typically small relative size and unique site situations required for development, they weren’t considered explicitly in the Technology Assessment or included in the integration analysis of this IRP. Vectren believes these technologies may be considered for viable projects in the future, primarily in the context of distributed generation as discussed in the following section, and that such projects will be duly evaluated as they develop.

November 2014 Page 113

2014 Integrated Resource Plan

This page intentionally left blank for formatting purposes

November 2014 Page 114

2014 Integrated Resource Plan

CHAPTER 7 RENEWABLES and CLEAN ENERGY

November 2014 Page 115

2014 Integrated Resource Plan

CURRENT PROJECTS Vectren currently receives renewable energy from three projects: two purchase power contracts from Indiana wind projects and one landfill methane gas project. Benton County Wind Farm The Benton County Wind Farm, located in Benton County, Indiana, began providing electricity to Vectren in May 2007 under a 20 year purchase power agreement. The nominal nameplate rating for this contract is 30 MW, and the expected annual energy to Vectren from this project is 76,500 MWh. Fowler Ridge II Wind Farm Vectren began receiving energy from the Fowler Ridge II wind farm, also located in Benton County, Indiana in December of 2009 under a 20 year purchase power agreement. The nominal nameplate rating for this contract is 50 MW, and the expected annual energy to Vectren from this project is 130,500 MWh. Blackfoot Landfill Gas Project Vectren owns the Blackfoot Landfill Clean Energy Project located in Pike County, Indiana. Vectren officially took over ownership of this project on June 22, 2009. This facility consists of 2 internal combustion engine-generator sets that burn methane gas collected from the adjacent Blackfoot Landfill. Total nameplate capacity is 3.2 MW gross combined for the two machines.

Vectren projects to produce approximately

15,000 MWh per year from this facility. Pending future expansion of the Blackfoot landfill and corresponding development of a viable gas field, Vectren may consider adding an additional generator set to this facility at some point in the future. RENEWABLE ENERGY CREDITS In addition to participation in actual renewable energy projects, both through ownership and purchase power agreements, Vectren will also consider purchasing renewable energy credits (RECs) to meet future renewable mandates. Vectren will monitor the November 2014 Page 116

2014 Integrated Resource Plan

market development for RECs over the next several years to determine the soundness of such a strategy. ADDITIONAL RENEWABLE AND CLEAN ENERGY CONSIDERATIONS Vectren modeled generation characteristics for output at time of peak load and capacity factor based on its geographic footprint. Additional wind generation with characteristics similar to Vectren’s existing wind PPA’s was also considered. Demand side management programs were considered as clean energy resource options and competed directly with other supply side options in the model.

November 2014 Page 117

2014 Integrated Resource Plan

Table 7-1 Clean Energy Projections Clean Energy Source

Year

Retail Sales before conservation programs

Wind Generation

Landfill Gas Generation

Conservation Programs

Year-Over-Year Conservation Increase

CustomerOwned DG

GWh

GWh

GWh

GWh

GWh

GWh

Vectren Clean Energy % of sales

2014

5,832

207.0

15

157

1

7%

2015

5,991

207.0

15

182

26

1

7%

2016

6,040

207.0

15

208

26

2

8%

2017

5,645

207.0

15

233

25

3

9%

2018

5,661

207.0

15

258

25

3

9%

2019

5,680

207.0

15

283

25

5

9%

2020

5,699

207.0

15

296

13

7

9%

2021

5,710

207.0

15

309

13

9

10%

2022

5,729

207.0

15

321

13

12

10%

2023

5,746

207.0

15

334

13

17

10%

2024

5,769

207.0

15

347

13

23

10%

2025

5,782

207.0

15

360

13

32

11%

2026

5,801

207.0

15

373

13

37

11%

2027

5,825

207.0

15

386

13

42

11%

2028

5,860

207.0

15

399

13

48

12%

2029

5,884

207.0

15

412

13

55

12%

2030

5,913

207.0

15

426

13

62

12%

2031

5,942

207.0

15

439

13

71

13%

2032

5,985

207.0

15

453

14

81

13%

2033

6,018

207.0

15

466

14

93

13%

2034

6,060

207.0

15

480

14

106

14%

November 2014 Page 118

2014 Integrated Resource Plan

This page intentionally left blank for formatting purposes

November 2014 Page 119

2014 Integrated Resource Plan

CHAPTER 8 DSM RESOURCES

November 2014 Page 120

2014 Integrated Resource Plan

INTRODUCTION The demand-side resource assessment process is based on a sequential series of steps designed to accurately reflect Vectren’s markets and identify the options which are most reasonable, relevant, and cost-effective. It is also designed to incorporate the guidelines from the IURC. This chapter presents a discussion of the planning and screening process, identification of the program concepts, and a listing of the demand-side management (DSM) options passed for integration. Additionally, IRP DSM modeling is discussed. HISTORICAL PERFORMANCE Since 1992, Vectren has utilized DSM as a means of reducing customer load and thereby providing reliable electric service to its customers. Historically, DSM programs provided both peak demand and energy reductions. DSM programs were approved by the Commission and implemented pursuant to IURC orders. These programs were implemented, modified, and discontinued when necessary based on program evaluations. Vectren has managed the programs in an efficient and cost effective manner, and the load reductions and energy savings from the programs have been significant. Between 2010 and 2013, Vectren DSM programs reduced demand by over 25,000 kW and provided annual incremental energy savings of over 130,000,000 kWh.

It is

anticipated that in 2014, Vectren will save an incremental 58,000,000 kWh of gross energy savings and approximately 15,000 kW in demand savings. Vectren also operates a Direct Load Control (DLC) program that reduces residential and small commercial air-conditioning and water heating electricity loads during summer peak hours. This demand response program commenced in 1992 and over 27,000 customers are enrolled with approximately 17 MW of peak reduction capacity.

November 2014 Page 121

2014 Integrated Resource Plan

EXISTING DSM RESOURCES and PROGRAMS Tariff Based Resources Vectren has offered tariff based DSM resource options to customers for a number of years. Consistent with a settlement approved in 2007 in Cause No. 43111, the Demand Side Management Adjustment (“DSMA”) was created to specifically recover all of Vectren's DSM costs, including (at that time) a DLC Component. The Commission, in its order in Cause No. 43427, authorized Vectren to include both Core and Core-Plus DSM Program Costs and related incentives in an Energy Efficiency Funding Component ("EEFC") of the DSMA. The EEFC supports the Company's efforts to help customers reduce their consumption of electricity and related impacts on peak demand. It is designed to recover the costs of Commission-approved DSM programs from all customers receiving the benefit of these programs. In Cause Nos. 43427, 43938, and 44318, the Commission approved recovery of the cost of Conservation Programs via the EEFC. This rider is available to rate schedule RS, B, SGS, DGS, MLA, OSS, LP, and HLF customers. Interruptible Rates In addition to the DSM programs described in this chapter, Vectren has offered interruptible rate programs for commercial and industrial customers. Vectren currently has approximately 47 MW of interruptible load under contract, not including the DLC Program. In addition to the riders listed below, Vectren has one customer on a special contract interruptible rate (as approved by the IURC), that makes up approximately 20 MW of the total 47 MW of interruptible load. Rider IP – 2 Interruptible Power Service This rider is available to rate schedule DGS, OSS, LP, and HLF customers with an interruptible demand of at least 200 kW who were taking service under this rider during September 1997. This rider is closed to new participants. This rider currently has two customers that represent approximately 6 MW of the total interruptible load. November 2014 Page 122

2014 Integrated Resource Plan

Rider IC Interruptible Contract Rider This rider is available to any rate schedule LP or HLF customer electric who can provide for not less than 1,000 kVa of interruptible demand during peak periods. This rider currently has two customers that represent approximately 21MW of the total interruptible load. Rider IO Interruptible Option Rider This rider is available to any rate schedule DGS, MLA, OSS, LP, or HLF customer who will interrupt a portion of their normal electrical load during periods of request from Vectren. A Customer’s estimated load interruption capability must exceed 250 kW to be eligible. This rider is not applicable to service that is otherwise interruptible or subject to displacement under rate schedules or riders of Vectren. Customers currently taking service under Vectren’s rider IP – 2, which is closed to new business, may apply for service under this rider, if eligible, for the balance or renewal of the existing contracts. Direct Load Control (DLC) The DLC program provides remote dispatch control for residential and small commercial air conditioning, electric water heating and pool pumps (on existing units only) through radio controlled load management receivers (LMR). The DLC program was implemented in April 1992 by Vectren, with the objective of reducing summer peak demand by direct, temporary cycling of participating central air conditioners and heat pumps and by shedding connected water heating and pool pump loads. Participating customers receive credits on their bills during the months of June through September based on the number and type of equipment participating in the program. The DLC program was identified, in 2007, as part of Vectren’s DSM Market Assessment study, prepared by Forefront Economics Inc. and H. Gil Peach & Associates LLC, as “…of high quality and notable for its participation and program longevity.” Vectren’s customers have achieved significant benefits from the existing DLC program.

November 2014 Page 123

2014 Integrated Resource Plan

The program consists of the remote dispatch and control of a DLC switch installed on participating customers’ central cooling units (central air conditioners and heat pumps), as well as electric water heating units where a DLC switch is also installed on the central cooling unit. Vectren can initiate events to reduce air-conditioning and waterheating electric loads during summer peak hours. Vectren can initiate a load control event for several reasons, including: to balance utility system supply and demand, to alleviate transmission or distribution constraints, or to respond to load curtailment requests from the Midcontinent Independent Transmission System Operator, Inc. (MISO), the regional electricity transmission grid authority. The control of central cooling units is typically a 50% cycling strategy and involves cycling the compressor off for 15 minutes out of every half hour during the cycling period. The direct load control of water heating equipment utilizes a shedding strategy. This involves shutting off these units for the duration of the cycling period. Cycling periods can range between two and six hours in duration. Vectren manages the program internally and utilizes outside vendors for support services, including equipment installation and maintenance. Prospective goals for the program consist of maintaining load reduction capability and program participation while achieving high customer satisfaction. Vectren also utilizes an outside vendor, The Cadmus Group, to evaluate the DLC program and provide unbiased demand and energy savings estimates. The DLC system has the capability to obtain approximately 17 MW of peak reduction capacity from the DLC system. Over time, the operability of the DLC switches can decline for a variety of reasons, including mechanical failure, contractor or customer disconnection, and lack of re-installation when customer equipment is replaced.

In

order to continue to obtain the peak demand response benefits from the DLC system, Vectren requested and received Commission approval of a multi-year DLC Inspection & Maintenance Program in Cause No. 43839. This inspection process began in 2011 with approximately 25% of the DLC switches inspected annually and this process will be November 2014 Page 124

2014 Integrated Resource Plan

completed early in 2015. Vectren has proposed in Cause No. 43405 DSMA 12 to continue ongoing maintenance of DLC switches on a five (5) year cycle with approximately 20% inspected annually.

The work will continue to be conducted by

trained vendors for both the inspection and replacement components of the program. By investing in the inspection and maintenance of the DLC system, Vectren can continue its ability to rely on this demand reduction resource as part of its resource planning. As of May 2014, Vectren’s DLC Program had approximately 27,040 residential customers and 530 commercial customers with a combined total of over 36,000 switches. Note that a customer may have more than one switch at a residence or business. Cause No. 43839 – Rate Design In Cause No. 43839, approved by the IURC on May 3, 2011, specific structural rate modifications were proposed by Vectren to better align Vectren’s rate design to encourage conservation. These structural changes include: 

For all rate schedules, Vectren separated its variable costs from its fixed costs. These changes are intended, among other things, to provide more clarity and transparency in the rate schedules as to the variable costs that Vectren customers can avoid as customers reduce usage.

Combined the customers under Rate A (the "Standard" customers) and Rate EH (the "Transitional" customers) into a single rate schedule, called Rate RS Residential Service. The results of these changes resulted in the elimination of the Rate A declining block rate design in favor of a single block rate design for the Rate RS - Standard customer group versus the previous declining block rates. The transition from a declining block rate design to a flat block rate design has been recognized as a method to encourage energy conservation.

The availability of Rate RS-Transitional was closed to new customers on May 3, 2012 in order to eliminate the promotion of all-electric space heating. A transition November 2014 Page 125

2014 Integrated Resource Plan

plan to gradually move the existing Rate RS-Transitional customers to RSStandard was to be filed for the Commission’s consideration within two years of Vectren’s most recent electric rate case on May 3, 2011. Vectren filed with the Commission a report on the Transition Plan on April 23, 2013 and recommended that any transition plan be considered in the next base rate case. The Commission has not yet ruled on this matter. 

The availability of the commercial Rate OSS (Off Season Service) was also closed to new customers on May 3, 2012 in order to eliminate the promotion of all-electric space heating. A transition plan to gradually move the existing Rate OSS customers to a comparable Rate DGS was to be filed for the Commission's consideration within two years of Vectren’s most recent electric rate case on May 3, 2011. Vectren filed with the Commission a report on the Transition Plan on April 23, 2013 and recommended that any transition plan be considered in the next base rate case. The Commission has not yet ruled on this matter.

In Vectren’s last electric base rate case, the Company proposed a decoupling mechanism that would break the link between recovery of fixed costs and energy sales in order to eliminate the financial harm to the Company caused when customers reduce their electric usage, thereby supporting the Company’s ability to aggressively promote energy conservation. The Commission ultimately denied this request in their April 27, 2011 Order. The rate structure listed above is reflected in the long term sales and demand forecast. MISO DR Program Vectren rider DR provides qualifying customers the optional opportunity to reduce their electric costs through customer provision of a load reduction during MISO high price periods and declared emergency events.

Rider DR currently offers two programs,

emergency demand response (“EDR”) and demand response resource Type 1 (“DRR-1”) energy programs.

November 2014 Page 126

2014 Integrated Resource Plan

Rider DR is applicable to any customer served under rates DGS or OSS with prior year maximum demand greater than 70 kW, MLA, LP, or HLF. A customer may participate in the rider DR only with kVa or kW curtailment load not under obligation pursuant to rider IC or IO or special contract. Customers must offer Vectren a minimum of one (1) MW of load reduction, or the greater minimum load reduction requirement that may be specified by the applicable MISO BPM for the type of resource offered by customer. A customer may participate in an aggregation as described in the Rider DR in order to meet the minimum requirement. Vectren currently does not have any customers participating in rider DR. Net Metering – Rider NM Rider NM allows certain customers to install renewable generation facilities and return any energy not used by the customer from such facilities to the grid. On July 13, 2011 the Commission published an amended net metering rule,

which included additional

modifications to the rules, including eligibility to all customer classes, increase to the size of net metering facilities (1 MW) and an increase in the amount of net metering allowed (1% of most recent summer peak load or approximately 11.5 MW). The new rules also required that at least forty percent (40%) of the amount of net metering allowed would be reserved solely for participation by residential customers. Vectren has worked with customers over the past several years to facilitate the implementation of net metering installations. As of July 1st, 2014, Vectren had 69 net metering customers with a total nameplate capacity of 474 kW. Smart Grid Resources Smart Grid technology has the potential to enable higher levels of reliability, energy efficiency and demand response, as well as improved evaluation, measurement, and verification of energy efficiency and demand response efforts. Reliability can be improved through distribution automation (DA) enhancements. These enhancements November 2014 Page 127

2014 Integrated Resource Plan

can provide operators with real-time information that allows them to make operational decisions more quickly to restore customers following an outage or possibly avoiding the outage completely. Additionally the enhancements can provide automation that can identify fault location, isolate and restore the customers quickly without operator intervention. The advanced metering infrastructure (AMI) portion of a Smart Grid project, as well as new dynamic pricing offerings, enable those customers who decide to actively manage their energy consumption to have access to significantly more information via enhanced communication. This provides those customers a better understanding and more control of their energy consumption decisions and the resulting energy bills. These improvements can provide benefits toward carbon foot print reduction as a result of the overall lowered energy consumption. The potential DSM benefits related to Smart Grid include: •

Peak reductions resulting from enabling Vectren customers to actively participate in demand response programs via dynamic pricing programs,

Enhanced load and usage data to the customer to foster increased customer conservation, and

Conservation voltage and line loss reductions due to the improved operating efficiency of the system.

In 2009, as part of the funding available from the United States Department of Energy (DOE) pursuant to American Recovery and Reinvestment Act (ARRA), Vectren conducted a business case analysis of the broad benefits of a Smart Grid implementation. According to the October 27, 2009 DOE announcement, Vectren did not receive a grant award for the Smart Grid project. Vectren re-evaluated the business case and determined that it would not be prudent to proceed with a broad Smart Grid project at this time due to net costs to customers. As part of this initiative Vectren completed the development of an initial Smart Grid strategy where it identified the need to invest in some foundational communication and information gathering technology in order to support future demand response and load management technology. The initial focus of the strategy is to build out a communication network that will support current November 2014 Page 128

2014 Integrated Resource Plan

and future Smart Grid technology, such as distribution Supervisory Control and Data Acquisition (SCADA), AMI, conservation voltage reduction (CVR), and system automation. Vectren has implemented a fiber optic communication path across its transmission network, connecting at both primary generating stations. Additional fiber installations are in progress across the transmission grid. The build out of the communication system has allowed Vectren to install and monitor additional SCADA points from its distribution substations. These SCADA installations are fundamental to the potential implementation of future conservation and voltage management programs, such as CVR, on the distribution network. Vectren will continue to monitor and evaluate Smart Grid technologies and customer acceptance of Smart Grid enabled energy efficiency and demand response. Vectren recognizes the potential benefits Smart Grid technology programs offer. While a comprehensive Smart Grid deployment is likely several years in the future, the goal of any Vectren Smart Grid project will be to improve reliability, reduce outage restoration times, and increase energy conservation capabilities. The foundational investments currently being made and those planned over the next few years will enhance Vectren’s ability to achieve these benefits. The potential impacts of a robust Smart Grid implementation that would include dynamic pricing, improved information or conservation voltage reduction have not been explicitly quantified in this IRP because no specific project of this magnitude has been proposed by Vectren. We continue to monitor these technologies for potential future implementation as they become cost effective for our customers. FEDERAL AND STATE ENERGY EFFICIENCY DEVELOPMENTS Federal – Codes, Standards and Legislation Energy efficiency policies are gaining momentum at both the state and Federal level. Although there are numerous activities going on at the state and Federal level the November 2014 Page 129

2014 Integrated Resource Plan

following are components of significant legislation that are approaching implementation, as well as new codes, standards and legislation being considered that will likely have an impact on energy efficiency in the planning horizon. 

On June 2, 2014, the EPA released its Clean Power Plan proposal that, if implemented, will for the first time regulate carbon dioxide (CO2) emissions from existing power plants at the U.S. federal level. The rule is designed to cut carbon pollution from power plants nationwide by 30 percent from 2005 levels. State compliance includes several paths, one of which is end use energy efficiency. While dependent on the actual state implementation plan, the proposed plan would require reductions of 0.57% starting in 2017 and ramping up to 1.5% annually from 2022-2036. By 2030, the EPA is looking for usage reductions in Indiana of 11.6% in cumulative savings and that number increases to 12.9% in cumulative savings by 2036. As this rule is developed and finalized,

it is likely to have potential significant impacts on energy

efficiency planning. 

The U.S. Department of Energy's Appliances and Equipment Standards Program develops test procedures and minimum efficiency standards for residential appliances and commercial equipment. On June 27, 2011, amended standards were issued for residential central air conditioners and heat pumps. Central air conditioners and central air conditioning heat pumps manufactured on or after January 1, 2015 will have minimum requirements for Seasonal

Energy

Efficiency

Ratios

(SEER)

and

Heating

Seasonal

Performance Factors (HSPF). State – Codes, Standards and Legislation Since 2009, Indiana has taken several significant steps to enhance energy efficiency policy in the state. 

In 2009, the IURC released the Phase II Generic DSM order. The order established statewide electric savings goals for utilities starting in 2010 at November 2014 Page 130

2014 Integrated Resource Plan

0.3% of average sales and ramping to 2% per year by 2019, The Phase II order also defined a list of five (5) Core DSM programs to be offered by a statewide Third Party Administrator (TPA) and allowed utilities the option to offer Core Plus programs in an effort to reach the 2% goal. 

As a result, since 2012, a statewide TPA has been running Core DSM Programs in Indiana. In March 2014, the Indiana General Assembly passed legislation which modified DSM requirements in Indiana. Senate Enrolled Act No. 340 (“SEA 340”) removed requirements for mandatory statewide ”Core’ DSM programs and savings requirements established in the Phase II Order. SEA 340 also allows large C&I customers who meet certain criteria to opt-out of participation in utility sponsored DSM programs. Furthermore, the statute goes on to prohibit the Commission from requiring jurisdictional electric utilities to meet the Phase II Order energy savings targets after December 31, 2014 and prohibits jurisdictional electric utilities from renewing or extending an existing contract or entering into a new contract with a statewide third party administrator for an energy efficiency program as established in the Phase II Order.

As a result of SEA 340, Vectren filed and received approval for a one year DSM plan for 2015 under Cause No. 44495 with a savings target of 1% of eligible customer sales.

VECTREN DSM STRATEGY Vectren has adopted a cultural change that encourages conservation and efficiency for both its gas and electric customers. Vectren has embraced energy efficiency and actively promotes the benefits of energy efficiency to its employees and customers. Vectren has taken serious steps to implement this cultural change starting with its employees. Vectren encourages each employee, especially those with direct customer contact, to promote conservation. Internal communications and presentations, conservation flyers and handouts, meetings with community leaders, and formal training have all promoted this shift. This cultural shift was a motivating factor in launching a November 2014 Page 131

2014 Integrated Resource Plan

new Vectren motto of "Live Smart" in order to further emphasize efficiency. Vectren’s purpose statement is the foundation of the Vectren Strategy related to DSM: Purpose With a focus on the need to conserve natural resources, we provide energy and related solutions that make our customers productive, comfortable and secure. Customers are a key component of Vectren’s values, and Vectren knows success comes from understanding its customers and actively helping them to use energy efficiently. Vectren will continue to offer cost-effective DSM to assist customers in managing their energy bills and meet future energy requirements. Vectren will include an on-going level of Vectren sponsored DSM in the load forecast and will also consider additional DSM as a source of new supply in meeting future electric service requirements (discussed further in the IRP DSM modeling section of this chapter). DSM savings levels in the load forecast include DSM energy efficiency programs available to all customer classes and a 1% annual savings targets for 2015-2019 and .5% annually thereafter. The 1% of eligible annual savings target assumes that 70% of eligible large customer load will optout of DSM programs using the provision provided in SEA340.1 The load forecast also includes an ongoing level of energy efficiency related to codes and standards embedded in the load forecast projections. Ongoing DSM is also important given the integration of Vectren’s gas and electric efficiency programs. DSM PLANNING PROCESS The following outlines Vectren’s planning process in support of Vectren’s strategy to identify cost effective energy efficiency resources. In 2006, as a result of a settlement in

1

Vectren assumes that 80% of large customers will opt out of Vectren sponsored DSM programs; however, 70% was selected for large sales modeling to capture large customer energy efficiency projects outside of Vectren sponsored programs.

November 2014 Page 132

2014 Integrated Resource Plan

Cause No. 42861, the DSM Collaborative was formed, including Vectren and the Indiana Office of Utility Consumer Counselor (“OUCC”) as voting members.

The

Collaborative provided input in the planning of Vectren’s proposed DSM programs. The Oversight Board was formed as a result of Cause No. 43427 and was given authority to govern Vectren’sElectric DSM Programs. When formed, the Oversight Board included Vectren and the OUCC as voting members. The Citizens Action Coalition (“CAC”) was added as a voting member of the Oversight Board in 2013 as a result of Cause No. 44318. The IURC Phase II Order in Cause No. 42693 issued on December 9, 2009 established energy saving goals for all jurisdictional utilities in Indiana. The Phase II Order required all jurisdictional utilities to implement five specified programs, which the Commission termed Core Programs.

The Core Programs were administered by a third party

administrator (TPA) selected through a process involving the Demand Side Coordination Committee composed of jurisdictional Investor-Owned Utilities (IOU’s) and other pertinent key stakeholders. Additionally, the Commission recognized that achieving the goals set out in the Phase II Order would not be possible with Core Programs alone and encouraged the utilities to implement Core Plus Programs to assist in reaching the annual savings goals. Core Plus programs are those programs implemented by the jurisdictional electric utilities in Indiana designed to fill the gap between savings achieved by the Core programs and the savings targets established by the Commission in the Phase II Order. To develop its own set of Core Plus programs, Vectren modified existing programs approved in Cause No. 43427 and added new programs, which were approved on August 31, 2011 in Cause No. 43938. During this period, Vectren also proceeded to integrate some of its electric programs with existing gas DSM programs. However, with the passage of SEA 340, mandatory statewide ”Core” DSM programs and savings requirements established in the Phase II Order have been removed as of November 2014 Page 133

2014 Integrated Resource Plan

December 31, 2014 and large C&I customers who meet certain criteria (“Qualifying Customers”) are allowed to opt-out of participation in Company sponsored energy efficiency programs. As a result, Vectren has implemented an opt-out process as defined in IURC Cause No. 44441 to allow Qualifying Customers to opt-out. This process includes defined annual opt-out and opt-in periods. The plan that Vectren initially filed for 2015 in IURC Cause No. 44495 on May 31, 2014 assumed a 50% level of opt-out. During the initial opt-out period effective July 1, 2014, approximately 71% of eligible large C&I retail sales opted out of participation in Company sponsored DSM. The higher than anticipated opt-out required Vectren to adjust the 2015 Plan to reflect lower spending and lower available savings potential because of the additional portion of the load that is no longer participating in DSM programs. There is an additional optout period in the fall of 2014 effective January 1, 2015. As a result, Vectren revised the 2015 Plan to adjust for an 80% opt-out level effective January 1, 2015. The revised plan was approved by the Oversight Board and is still pending Commission approval as part of Cause No. 44495. The 2015 Plan was developed during an IRP planning period; therefore, the 2014 IRP could not serve as a key input into the 2015 Plan. As a result, the avoided cost basis from the 2011 IRP was used to develop the 2015 Plan. The framework for the 2015 Plan is a continuation of programs offered in 2014, at a savings level of 1.2% of sales (adjusted for the assumption that 80% of Qualifying Customers will opt-out of the programs). However, there were many steps involved in developing the 2015 Plan. The objective of these steps was to develop a plan based on market-specific information for Vectren, which could be successfully implemented utilizing realistic assessments of achievable market potential. The first step in the process was retaining EnerNOC to complete a Market Potential Study1 (MPS), included in the Technical Appendix, section D. At the end of 2012, 1

Electric Demand Side Management: Market Potential Study and Action Plan, EnerNOC Utility Solutions Consulting, April 22, 2013

November 2014 Page 134

2014 Integrated Resource Plan

Vectren, with guidance from the Vectren Electric Oversight Board, engaged EnerNOC, Inc. to study its DSM market potential and develop an Action Plan. EnerNOC conducted a detailed, bottom-up assessment of the Vectren market in the Evansville metropolitan area to deliver a projection of baseline electric energy use, forecasts of the energy savings achievable through efficiency measures, and program designs and strategies to optimally deliver those savings.

The study developed technical, economic and

achievable potential estimates by sector, customer type and measure. According to the MPS, EnerNOC performed the following tasks in completing the study: 1. Conducted onsite energy consumption surveys with 30 of Vectren’s largest commercial and industrial customers in order to provide data and guidance for these market sectors that had not formerly received focused DSM program efforts. 2. Performed a market characterization to describe sector-level electricity use for the residential, commercial, and industrial sectors for the base year, 2011. This included using existing information contained in prior Vectren and Indiana studies, new information from the aforementioned onsite surveys with large customers, EnerNOC’s own databases and tools, and other secondary data sources such as the American Community Survey (ACS) and the Energy Information Administration (EIA). 3. Developed a baseline electricity forecast by sector, segment, and end use for 2011 through 2023. Results presented in this volume focus on the upcoming implementation years of 2015 through 2019. 4. Identified several hundred measures and estimated their effects in five tiers of measure-level energy efficiency potential: Technical, Economic, Achievable High, Achievable Recommended and Achievable Low. 5. Reviewed the current programs offered by Vectren in light of the study findings to make strategic program recommendations for achieving savings. 6. Created recommended program designs and action plans through 2019 representing the program potential for Vectren, basing them on the potential analysis and strategic recommendations developed in the previous steps. November 2014 Page 135

2014 Integrated Resource Plan

The EnerNOC MPS and other study information were used to help guide the plan design. Study analysis and results details can be found in the MPS and its appendices. For planning purposes Vectren used the “Recommended Achievable” scenario as a guide for developing the 2015 Plan. The second primary step in the planning process was to hire outside expertise to assist with the plan design and development. Vectren retained Morgan Marketing Partners to assist with designing the 2015 Plan. Rick Morgan, President of Morgan Marketing Partners, was the primary planner working with the Vectren team. The third primary step in the planning process was to obtain input from various sources to help develop and refine a workable plan. The first group providing input was Vectren’s DSM Program Managers who have been overseeing current Vectren programs. In addition, vendors and other implementation partners who operate the current programs were very involved in the process as well. They provided suggestions for program changes and enhancements. The vendors and partners also provided technical information about measures to include recommended incentives, estimates of participation and estimated implementation costs. These data provided a foundation for the 2015 Plan based on actual experience within Vectren’s territory. These companies also bring their experience operating programs for other utilities. Other sources of program information were also considered. Current evaluations were used for adjustments to inputs. In addition, best practices were researched and reviewed to gain insights into the program design of successful DSM programs implemented at other utilities. Once the plan was developed, Vectren obtained feedback and approval from the Oversight Board before finalizing.

November 2014 Page 136

2014 Integrated Resource Plan

DSM SCREENING RESULTS The last step of the planning process was the cost benefit analysis. Utilizing a cost / benefit model, the measures and programs were analyzed for cost effectiveness. The outputs include all the California Standard Practice Manual results including Total Resource Cost (TRC), Utility Cost Test (UCT), Participant and Ratepayer Impact Measure (RIM) tests. Inputs into the model include the following: participation rates, incentives paid, energy savings of the measure, life of the measure, implementation costs, administrative costs, incremental costs to the participant of the high efficiency measure, escalation rates and discount rates. Vectren considers the following tests and ensures that the portfolio passes the TRC test as this test includes the total costs and benefits to both the utility and the consumer. Table 8-4 below outlines the results of all tests. The model includes a full range of economic perspectives typically used in energy efficiency and DSM analytics. The perspectives include: 

Participant Test

Utility Cost Test

Ratepayer Impact Measure Test

Total Resource Cost Test

The cost effectiveness analysis produces two types of resulting metrics: 1. Net Benefits (dollars) = NPV ∑ benefits – NPV ∑ costs 2. Benefit Cost Ratio = NPV ∑ benefits ÷ NPV ∑ costs As stated above, the cost effectiveness analysis reflects four primary tests.

Each

reflects a distinct perspective and has a separate set of inputs reflecting the treatment of costs and benefits.

A summary of benefits and costs included in each cost

effectiveness test is shown below in Table 8-1.

November 2014 Page 137

2014 Integrated Resource Plan

Table 8-1 Vectren Cost Effectiveness Tests Benefits & Costs Summary Test Participant Cost Test

  

Benefits Incentive payments Annual bill savings Applicable tax credits

Costs   

Utility Cost Test (Program Administrator Cost Test)

 

Avoided energy costs Avoided capacity costs

 

Rate Impact Measure Test

Total Resource Cost Test

 

Avoided energy costs Avoided capacity costs

  

Avoided energy costs Avoided capacity costs Applicable participant tax credits

   

Incremental technology/equipment costs Incremental installation costs All program costs (startup, marketing, labor, evaluation, promotion, etc.) Utility/Administrator incentive costs All program costs (startup, marketing, labor, evaluation, promotion, etc.) Utility/Administrator incentive costs Lost revenue due to reduced energy bills All program costs (not including incentive costs) Incremental technology/equipment costs (whether paid by the participant or the utility)

The Participant Cost Test shows the value of the program from the perspective of the utility’s customer participating in the program. The test compares the participant’s bill savings over the life of the DSM program to the participant’s cost of participation. The Utility Cost Test shows the value of the program considering only avoided utility supply cost (based on the next unit of generation) in comparison to program costs. The Ratepayer Impact Measure (RIM) Test shows the impact of a program on all utility customers through impacts in average rates. This perspective also includes the estimates of revenue losses, which may be experienced by the utility as a result of the program.

November 2014 Page 138

2014 Integrated Resource Plan

The Total Resource Cost (TRC) Test shows the combined perspective of the utility and the participating customers. This test compares the level of benefits associated with the reduced energy supply costs to utility programs and participant costs. In completing the tests listed above, Vectren used 7.29% as the weighted average cost of capital, which is the weighted cost of capital that was approved by the IURC on April 27, 2011 in Cause No. 43839. For the 2015 Plan, Vectren utilized the avoided costs from Table 8-4 in the 2011 IRP. The avoided costs listed below in Table 8-2 were not yet available when the 2015 Plan was developed and filed with the Commission. As the 2015 Action Plan is finalized in late 2014, Vectren will use the avoided costs from the table below and also for any future modeling of DSM programs for 2016 and beyond. Vectren conducts IRPs every two years. Note that The avoided generating capacity costs are reflective of the estimated replacement capital and fixed operations and maintenance cost for an F-class simple cycle gas turbine, as discussed in Table 6-1 SGCT Classes. The operating and capital costs are assumed to escalate with inflation throughout the study period. The cost assumptions can be found in the Technical Appendix, section B. Transmission and distribution capacity are accounted for within the transmission and distribution avoided cost. Vectren’s planning reserve margin position is not factored into the avoided capacity cost as presented. Under the base sales forecast, Vectren does not require additional capacity to meet the planning reserve margin requirement throughout the study period. The marginal energy cost are reflective of the modeled Vectren system marginal cost of energy from the base scenario under base assumptions. This included variable transaction purchase, emission costs for CO2 starting in 2020, operation and maintenance, and fuel costs. The marginal system cost reflects the modeled spinning reserve requirement and adjusted sales forecasts accounting for transmission and distribution losses. The variable system costs reflected in this calculation can be found in the Technical Appendix, section B.

November 2014 Page 139

2014 Integrated Resource Plan

Table 8-2 Vectren Avoided Costs

2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034

Capacity Surplus / (Deficit) MW 81 80 102 106 109 109 109 108 108 108 109 109 108 106 105 104 104 102 101 100

Generation Avoided Cost $/kW $104.01 $105.67 $107.36 $109.08 $110.82 $112.60 $114.40 $116.23 $118.09 $119.98 $121.90 $123.85 $125.83 $127.84 $129.89 $131.97 $134.08 $136.22 $138.40 $140.62

Total Capacity Avoided Cost $/kW $114.41 $116.24 $118.10 $119.99 $121.91 $123.86 $125.84 $127.85 $129.90 $131.98 $134.09 $136.23 $138.41 $140.63 $142.88 $145.16 $147.49 $149.85 $152.24 $154.68

Transmission / Distribution Avoided Cost $/kW $10.40 $10.57 $10.74 $10.91 $11.08 $11.26 $11.44 $11.62 $11.81 $12.00 $12.19 $12.38 $12.58 $12.78 $12.99 $13.20 $13.41 $13.62 $13.84 $14.06

Marginal Energy Cost $/MWh $36.94 $43.32 $45.01 $47.58 $49.42 $63.16 $65.23 $67.44 $69.84 $73.54 $76.04 $79.06 $81.84 $85.11 $89.11 $92.79 $96.21 $100.77 $105.98 $110.93

Marginal Energy Cost $/kWh $0.0369 $0.0433 $0.0450 $0.0476 $0.0494 $0.0632 $0.0652 $0.0674 $0.0698 $0.0735 $0.0760 $0.0791 $0.0818 $0.0851 $0.0891 $0.0928 $0.0962 $0.1008 $0.1060 $0.1109

A review of the benefit/cost results for each of the technologies considered in the screening analysis is detailed in Table 8-3. Note that measures with a benefit-cost ration of 0.00 indicates no direct technology costs are applied. Table 8-3 Vectren DSM Technology Screening Results Residential Technology Analysis Results

Participant Test ID 1 2 3 4

Program Name 30% Infil. Reduction Electric Furnace no CAC V IQW109 30% Infil. Reduction Electric Furnace w/ CAC V IQW107 30% Infil. Reduction Gas Furnace no CAC V IQW111 30% Infil. Reduction Gas Furnace w/ CAC

NPV $

BCR

RIM Test NPV $

TRC Test BCR

NPV $

BCR

UCT Test NPV $

BCR

$458

N/A

$118

1.11

$785

3.17

$785

3.17

$55,076

N/A

$15,424

1.13

$95,634

3.23

$95,634

3.23

$55 $19,901

N/A N/A

($558) ($58,161)

0.18

($478) ($29,178)

0.21

($478) ($29,178)

0.21

November 2014 Page 140

2014 Integrated Resource Plan

Participant Test ID

5

Program Name V IQW110 30% Infil. Reduction Heat Pump V IQW108

NPV $

BCR

RIM Test NPV $

TRC Test BCR 0.44

NPV $

BCR 0.61

UCT Test NPV $

BCR 0.61

$6,012

N/A

$226

1.02

$8,981

2.63

$8,981

2.63

$16,471

N/A

$8,159

1.29

$31,187

7.34

$31,187

7.34

7

5th Grade Kit- Air Filter Alarm V RES113 5th Grade Kit- Bathroom Aerator 1.0 gpm V RES110

$5,758

N/A

$671

1.07

$7,862

3.52

$7,862

3.52

8

5th Grade Kit- CFL - 13 W V RES111

$40,416

N/A

($28,761)

0.61

$15,287

1.51

$15,287

1.51

9

5th Grade Kit- CFL - 23 W V RES112 5th Grade Kit- Kitchen Flip Aerator 1.5 gpm V RES109

$65,788

N/A

($43,510)

0.63

$28,191

1.63

$28,191

1.63

$2,879

N/A

($1,431)

0.79

$2,165

1.65

$2,165

1.65

5th Grade Kit- LED Nightlight V RES114 5th Grade Kit- Low Flow Showerhead 1.5 gpm V RES108

$16,172

N/A

($15,326)

0.50

$4,874

1.46

$4,874

1.46

$35,128

N/A

($7,034)

0.89

$31,250

2.29

$31,250

2.29

($7,347)

0.57

($2,518)

0.77

($2,546)

0.77

$1,427

1.20

($8,537)

0.50

($1,328)

0.87

($2,546)

0.77

$2,617

1.44

($2,249)

0.46

$127

1.05

($1,032)

0.73

$1,450

2.04

($2,074)

0.51

($48)

0.98

($1,032)

0.73

$1,275

1.81

$84,943

5.32

($298)

1.00

$63,369

2.69

$63,612

2.71

$385,674

5.90

($3,125)

0.99

$269,452

2.67

$268,064

2.64

$3,288

N/A

($13,850)

0.35

($9,061)

0.46

($9,061)

0.46

6

10 11 12

15

Air Source Heat Pump 16 SEER - no gas available REP113 Air Source Heat Pump 16 SEER -gas available REP127 Air Source Heat Pump 18 SEER - gas available REP129

16

Air Source Heat Pump 18 SEER - no gas available REP115

13 14

17 18

Appliance Recycling Freezers ARC102 Appliance Recycling Refrigerators ARC101

19

Attic Insulation V IQW112

20

Audit Recommendations IQW V IQW114

$11,374

N/A

($40,699)

0.29

($29,325)

0.36

($29,325)

0.36

21

Audit Recommendations V HEA116

$28,561

N/A

($69,232)

0.35

($44,098)

0.45

($44,098)

0.45

22

Bathroom Aerator IQW V IQW103

$2,874

N/A

($615)

0.90

$3,125

2.21

$3,125

2.21

23

Bathroom Aerator V HEA112

$37,299

N/A

$3,890

1.06

$46,598

3.48

$46,598

3.48

24

Central Air Conditioner 16 SEER REP 116

($21,517)

0.75

($19,160)

0.73

($4,056)

0.93

$3,801

1.08

25

Central Air Conditioner 18 SEER REP 117

($40,415)

0.68

($11,391)

0.89

($19,244)

0.83

$28,384

1.43

26

CFL 0-15W RLT104

$611,084

3.01

($105,148)

0.84

$300,024

2.27

$347,738

2.85

27

CFL 16-20W RLT105

$619,795

3.46

($77,706)

0.87

$320,977

2.55

$360,400

3.15

28

CFL 21W or Greater RLT106

$591,307

4.09

($55,275)

0.90

$314,606

2.85

$344,554

3.46

29

Compact Fluorescent Lamps V HEA101 Compact Fluorescent Lamps IQW V IQW101 Dual Fuel Air Sourc Heat Pump 16 SEER REP128

$309,769

N/A

($390,021)

0.45

($80,547)

0.80

($80,547)

0.80

$69,004

N/A

($127,952)

0.38

($49,613)

0.62

($49,613)

0.62

($8,537)

0.50

($1,328)

0.87

($2,546)

0.77

$2,617

1.44

Duct Sealing Electric Heat Pump REP108 Duct Sealing Electric Resistive Furnace REP109 Duct Sealing Gas Heating with A/C REP107 Ductless Heat Pump 17 SEER 9.5 HSPF REP123 Ductless Heat Pump 19 SEER 9.5 HSPF REP124 Ductless Heat Pump 21 SEER 10.0 HSPF REP125 Ductless Heat Pump 23 SEER 10.0 HSPF REP126

$20,945

1.89

$5,993

1.10

$38,174

2.27

$36,074

2.13

$10,758

4.42

($1,045)

0.95

$13,411

2.65

$13,131

2.56

$1,482

1.02

$49,405

1.46

$77,922

1.99

$101,547

2.84

$2,469

2.84

($1,590)

0.73

$1,603

1.61

$1,628

1.63

$1,819

1.90

($1,508)

0.74

$1,174

1.37

$1,735

1.67

$790

1.59

($904)

0.71

$391

1.21

$765

1.51

$461

1.27

($869)

0.73

$165

1.08

$808

1.54

30 31 32 33 34 35 36 37 38

November 2014 Page 141

2014 Integrated Resource Plan

Participant Test ID 39

Program Name Duel Fuel Air Source Heat Pump 18 SEER REP130

40

NPV $

BCR

RIM Test NPV $

TRC Test BCR

NPV $

BCR

UCT Test NPV $

BCR

($2,249)

0.46

$127

1.05

($1,032)

0.73

$1,450

2.04

ECM HVAC Motor REP118

$9,831

1.11

($49,672)

0.56

($17,936)

0.78

($8,311)

0.88

41

Energy Star Ceiling Fans RLT112

($165)

0.74

($59)

0.84

($29)

0.91

$172

2.26

42

Energy Star Fixtures RLT111

$4,481

1.15

($3,400)

0.88

$8,869

1.54

$15,622

2.63

43

Energy Star Reflector CFL V RLT102

$4,738

1.14

($10,011)

0.65

($1,997)

0.90

$8,065

1.78

44

Energy Star Reflector LED V RLT103

$4,345

1.72

($1,530)

0.87

$5,336

2.01

$7,749

3.70

45

Energy Star Specialty CFL V RLT101

$4,738

1.14

($10,011)

0.65

($1,997)

0.90

$8,065

1.78

46

$20,061

N/A

$3,847

1.09

$33,063

3.59

$33,063

3.59

47

Furnace Filter Whistle IQW V IQW106 Gold Star HERS =

[PDF] By Southern Indiana Gas and Electric Company d/b/a Vectren Energy Delivery of Indiana, Incorporated - Free Download PDF (2024)

References

Top Articles
Latest Posts
Article information

Author: Velia Krajcik

Last Updated:

Views: 6170

Rating: 4.3 / 5 (54 voted)

Reviews: 93% of readers found this page helpful

Author information

Name: Velia Krajcik

Birthday: 1996-07-27

Address: 520 Balistreri Mount, South Armand, OR 60528

Phone: +466880739437

Job: Future Retail Associate

Hobby: Polo, Scouting, Worldbuilding, Cosplaying, Photography, Rowing, Nordic skating

Introduction: My name is Velia Krajcik, I am a handsome, clean, lucky, gleaming, magnificent, proud, glorious person who loves writing and wants to share my knowledge and understanding with you.